DR9801-CS 98112412/02/98 WED 10:40 FAX 214 739 0095 HALFF ASSOC ~002 Weekly Progress Report Offsite Drainage and Paving Improvements Progress Report No. 5 Date: November 24, 1998 Time: 8:30 AM Temp: 60's Weather: cloudy Contr. Wright Construction Crew: 0 Equip.: none Halff Associates arrived on site at approximately g:30 am on November 24 for construction observation. At the 60" RCP site at Fritz Drive and Freeport Parkway, nothing new has occurred since the November 10 observation. The trench is not up to grade at this time. Grading needs to be done around the headwall. Backfill needs to be placed around the headwall. At the 8'x 5' box culvert site, all of the box and both headwalls have been installed. Grading needs to be done around both headwalls. At the 54" REP and drive site at the intersection of Freeport Parkway and 1-635, all of the 54" RCP has been installed. Grading needs to be done along the site for the paving. The paving will not begin until the City Council has passed the Change Order #I on December 8, 1998. Date: December 1, 1998 Time: 10:30 AM Temp: mid 60's Weather: Clear, sunny Contr. Wright Construction Crew: 0 Equip.: none HalffAssociates arrived on site at approximately 10:30 am on December 1 for construction observation. Nothing new has occurred since the November 24 observation. According to Tim Mullikin of Wright Construction, the paving subcontractor will begin the street repair at Freeport Parkway and Southwestern on Thursday, December 3 and will pour the concrete on Tuesday, December 8. tt has been a pleasure working v6th you on this project. If you have any comments or questions, please eomaet me by phone at (214) 346-6246 or by fax at (214) 739-0095 Todd Jackson HALFF ASSOCIATES, INC. cc: Robert McCann, Catellus Development Corporation