DR9801-CS 981030 Weekly Progress Report Offsite Drainage and Paving Improvements Progress Report No. 2 Date: October 27, 1998 Time: 9:30 AM Tcmp: low 70's Weather: sunny, clear, light wind Contr. Wright Construction Crew: 10 Equip.: small backhoe, large backhoe, bull dozer, sheep's foot roller, front-end loader, 2 dump trucks HalffAssociates arrived on site at approximately 9:30 am on October 27 for construction observation. At the 60" RCP site at Fritz Drive and Freeport Parkway, 2 dump tracks were unloading native material from the excavation of the box culvert trench at. Southwestern and Freeport Parkway. At this time about 14 or 15 truck loads had been dumped on top of the 60" RCP alignment. No other equipment was on-site. The last joint on each oft. he 60" RCP lines was exposed. The headwall has not been constructed at this time. At the 8'x 5' box culvert site, approximately one-third of the box culvert sections have been installed starting at the down stream end. Most of the sections that have been installed have also been backiilled with native material and compacted. The large backhoe was excavating the trench and placing the box culvert sections into the french. The excavated material was being stockpiled next to the trench where the front- end loader was loading this material into the 2 dump trucks. The front-end loader was also dumping the rock embedment into the trench before each cuIvert section was placed in the trench. The dozer was spreading native material over the placed box culvert sections and a sheep's foot roller was compacting the native material. The small backhoe with a roller attached to the end of it was being used to compact the native material between the box culvert and the trench wall. Two crew members were in thc trench spreading the rock embedment with shovels and sealing the joints. All joints on the exposed sections appeared to be sealed. Two sections of the box culvert remained exposed on the down stream end where it will connect to a headwall. Surveyor's equipment was set up on site. Date: October 30, 1998 Time: 8:30 AM Temp: mid 70's Weather: Partly cloudy Contr. Wright Construction Crew: 9 Equip.: small backhoe, large backhoe, bull doZer, sheep's foot roller, front-end loader, 1 dump truck · 10/30/98 FRI 15:32 FAX 214 739 0095 HALFF ASSOC ~003 il HalffAssociates arrived on site at approximately 8:30 am on October 30 for construction observation. At the 60" RCP site at Fritz Drive and Freeport Parkway, 1 dump truck was unloading native material from the excavation of thc box culvert trench at Southwestern and Freeport Parkway. At this time about 5 or 6 truck loads had been dumped on top of ... the 60" RCP alignment. No other equipment was on-site. The last joint on each of the !i! i. 60" RCP lines was exposed. Thc headwall has not been constructed at this time. At the 8'x 5' box culvert site, approximately 90% of the box culvert sections have been installed from the down stream end to Freeport Parkway along Southwestern. Most of the sections . that have been installed have also been backfilled with native material and compacted. Thc large backhoe was excavating the trench and placing the box culvert sections into the trench. The excavated material was being stockpiled next to thc trench where the front- end loader was loading this material into the dump Iruck. The front-end loader was also dumping the rock embedment into the trench before each culvert section was placed in the trench. The dozer was spreading native material over the placed box culvert sections and a sheep's foot roller was compacting the native material. The small backhoe with a roller attached to the end of it was being used to compact the native material between the box culvert and the trench wall. Two crew members were in the trench spreading the rock embedment with shovels and sealing the joints. All joints on the exposed sections appeared to be sealed. Two sections of the box culvert remained exposed on the down stream end where it will connect to a headwall. Surveyor's equipment was set up on site. · Troy, the on-site forman for Wright Construction, said that the barricades for the traffic control on Freeport Parkway would arrive on Monday, November 2, 1998. i.i..:~.~ili: It has been a pleasure working with you on this project. If you have any comments or questions, please contact me by phone at (214) 346-6246 or by fax at (214) 739-0095 Todd Jackson HALFF ASSOCIATES, INC. cc: Robert McCann, Catellus Development Corporation