DR9801-CS 981020 10/20/98 TUE 16:59 FAX 214 739 0095 HALFF ASSOC ~002 · · Summary ' Offsite Drainage and Paving lmprovcment~ On-site Meeting No. 1 October 20, 1998 HalffAssociates arrived on site at approximately 10:00 am on October 20 to discuss construction and inspection issues. The meeting began approximately nt 11:00 am and concluded at approximately 12:30 pm. During this time discussions about cons~ction and inspection issues were held; however, not nil attendees were present for all discussions. I. Participants Name ~anization Phone Fax~E-mail Todd ,lackson Halff Associates 214-346-6246 214-739-0095 Matt Dorsett HalffAssociates 214-346-6243 214-739-0095 Jay Heame Wright Construction 817-481-2594 817-481-2369 Troy Wright Construction 817-481-2594 817-451-2369 Robert McCann Catellus Dev. Corp. 972-719-6128 972-719-6149 Keith Atkins Reed Engineering 214-350-5600 214-350-0019 Garreth Campbell City of Coppell 972-304-3685 972-304-3570 II. Issues Discussed Item Action Description 1.1 info Biweekly on-site meeting scheduled for Tuesdays at 10:30 am 1.2 Halff Halffwill be performing construction observation twice a week for the duration of the project. Halffwill be submitting a weekly report to Garreth Campbell about the construction observation. No particular format was requested by Mr. Campbell; however, he suggested just photo copying journal notes. ] .3 Wright A set of stamped construction drawings will be provided to Halff from Wright by courier. 1.4 Halff The proposed drive and 54" RCP design is changing and will be modified this week and sent to the city for review. 1.5 Wright Wri§ht will proceed from the 60" RCP to the 8'x5' box culvert. The drive and RCP will be completed last. !',,.,.~ .. 1.6 info Reed Engineering performed proctor tests on Thursday, October 15, 1998. ;~f'~' :i'' Reed arrived on-site October 19 and October 20 to perform additional testing; :~:: ~C however, they were unsuccessful due tO the constructiOn stage and bad weather. !:: 1.7 info Wright said they would be complete with the 60" RCP portion on Wednesday, October 21 (weather permitting) and begin working on the 8'x5' box culvert portion on Thursday, October 22. The utility locates and the construction staking have been performed for the box culvert portion. Wright said they anticipated the box culvert portion to take 9 working days to complete. 10/20/98 TUE 16:59 FAX 214 739 0095 HALFF AS$OC ~003 1.g info Halffhanded out a memo to Reed, Catellus, and Wright stating that Reed ne~s to send a copy of all materials testing rcsult~ to Catellus, Wright, Halff, and the City of Coppell. 1.9 Halff Wright asked where to put the spoils from the box culvert excavation. Cat¢llus said to use as fill material over the 60" RCP if it is the same type of material. Halffwill check the geote~ report to verify the material. (After review of the geot~ch report, the box culvert area contains the same type material as the 60" RCP area and can be used as backfill material) 1.10 Wright Wright stated that they are not going to compact the fill material over the 60" of the contract documents and construction specifications, Wright will be required to compact the fill material as stated in Section 04210, Pan III of the specifications.) Additions and corrections to these minutes should be sent to Todd Jackson by phone at (214) 346-6246 or by fax at (214) 739-0095 within five (5) working days. If no corrections are noted, minutes will be · assumed correct. HALFF ASSOCIATES, INC. Todd Jackson 10/23/98 FRI 10:19 FAX 214 739 0095 ItALFF ASSOC [~003 Weekly Progress Report Offsite Drainage and Paving Improvemcn~ Progress Report No. 1 Date: October 20, 1998 Time: 10:00 AM Temp: low 60's Weather: cloudy, light ra~ Con~. Wright Con~mc~on Crew: 4 Equip.: s~l ~c~oe, l~ge bac~oe, bull do~r, sheep's foot roller H~ff ~soc~tes ~wd on site a approximately 10:00 m on October 20 for co--etlon ob~aion. At ~s time ~e cons~ction crew was stopping work due to ~e rain. The ~ench was becoming ~11 of water ~d ~e l~ge bac~oe w~ having ~ouble m~euvefing in ~ mud. Up to ~s poin~ 60" RCP h~ been 1Md ~om ~e exi~ng he~w~l past ~e PT of ~e c~e ~d has been backfilled ~ naive martial just over ~e top of~e pip~. O~y 5 or 6 join~ on e~h line ~e exposed. ~ey have rock embe~ent ~der ~e pipe ~d ~ve ~en p~ally bac~ll~ ~ s~d mate~al. Not all of ~e joints have been ~aled d~ to ~e stoppage of work. Fo~een joints of 60" RCP ~11 rem~n on ~e gro~d to be ins~led. D~ing the ~ sto~, it sh~l ~ noted ~at only one of ~e ~0" RCPs w~ flo~ng ~ sto~ waer. The con, actor stated ~at ~e existing doublc 60" RCP was ~o-~ir~ ~11 wi~ silt ~d debris bcfore ~ey made thc conn~tion and ~a ~ey 'o~y did "a li~le bit" lo ~clog the exis2ng 60" pipes. The sto~ water tha was flo~ng in ~e one 60" pi~ was wasMng away ~e rock cmbe~ent ~demea~ it. It ~so sh~l bc noted ~at ~e gravel stoc~ile, s~d stockpile, top soil stockpilc, ~d 60" RCP ~e ~ing aored on prope~ ~a is not o~cd by Catellus Development Co~oraion. Wea~er ~i~ng, the con, clot ~cipatcs being completed ~ ~c doublc 60" RCP ~nion offs project by ~e end of We~esday, October 21,199~. Date: October 22, 1998 Time: 2:30 PM Temp: upper 70's Wea~er: sunny, blue skies, light wind Contr. Wright Construction Crew: 6 Equip-: small backhoe, large backhoe, bull dozer, sheep's foot roller Halff Associates arrived on site at approximately 2:30 PM on October 22 for consmiction observation. At the 60" RCP site at Fritz Drive and Freeport Parkway, 4 crew members were working on backfilling and compacting around the double 60" RCP. All the 60" RCP appeared to have been placed; only one joint remained on the bank. The dozer was