September 22, 2006
Tom Wouters
Realty Capital
99 Main Street, Suite 200
Colleyville TX 76034
RE Coppell/121 Office Park, Parking Lot Addition
Final Acceptance Conditions
Dear Mr Wouters
The referenced work appears to be essentially complete Two items are required for receiving final
acceptance They are as follow
1 Provide a maintenance bond from a registered surety for 50% of the contract value of work
performed m the public right-of--way and easements fora 2-year period stated as beginning on
the date of final acceptance from the City
2 Provide record drawings of the public improvements from the engineer to be submitted to City
of Coppell Engmeenng Dept.
When these two items have been recewed, your project will receive a final acceptance letter If you
have any questions, please call me at your earliest convenience
Sincerely, 1~
~~ ~ ~~G~
fl%~
Rick O'Dell
Construction Inspector
Office Phone 972/ 304-7090
Fax 972/304-3570
cc Keith R. Marvin, P E ,Assistant Crty Engineer
Glenn Hollowell, P.E ,Assistant Director of Public Works
Greg Jones, Chief Building Official
Tim Oates, Fire Marshal
With attachment Record-Drawing Content and Submittal Requirements to
Konstantme Bakmtas, P E
Baird Hampton & Brown, Inc
920 S Mam Street, Suite 190
Grapevine, TX 76051