Sandy Lk Oaks-CS060928DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM Sandy Lake Oaks Addition, Lot 1, Block A, Minor Plat to establish fire
lanes and various easements to allow for the development of a 13,110- square-
foot retail /office building on 1 543 acres of property located at the north east
corner of Sandy Lake and Moore Road, known as 632 Sandy Lake Road, at
the request of Chuck West, West and Associates
STAFF REP.: Gary Sieb PROJECT ID# MP -06 -0052
DRC DA TE : September 28, 2006 and October 5, 2006
CONTACT. Kenneth M. Griffin, P.E., Din of Engineering /Public Works 972/304 -3686
COMMENT STATUS: I ✓PRELIMINARY I rT� I n�T�M
Utility Plans
1 Turn on layer showing sewer line
2 The fire line should be looped.
3 Minimum fire line size is 8"
4 Will there be an irrigation meter" There may be an existing service to the southwest corner
of this lot. Can this be used for irrigation
Plat
1 Minimum easement for DDC Vault should be 25'x 25'
2 If the fire line is required to be looped, another easement and vault will be required.
For your information, we are providing the following estimated fees These fees are based on
the information provided, and may change prior to finalizing the project.
Roadway Impact Fee $15,575
Water Impact Fee $7,050
Wastewater Impact Fee $4,800
In addition, construction inspection fees in the amount of 2% of private paving, drainage, water
and sewer and 4% of public work will be collected at the time of permrttmg.
See the attached sheet entitled "General Engineering Plan Review Process" for information on
review process
DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM: Sandy Lake Oaks Addition, Lot 1, Block A, Site Plan to allow for the
development of a 13,110- square -foot retail /office building on 1 543 acres of
property located at the north east corner of Sandy Lake and Moore Road,
known as 632 Sandy Lake Road, at the request of Chuck West, West and
Associates
STAFF REP.: Gary Sieb PROJECT ID# SPA -06 -0051
DRC DATE: September 28, 2006 and October 5, 2006
r T ACT: Kenneth M. Griffin, P.E., Dir.ofEngineering /Public Works 972/304 -3686
OMMENT STATUS: ✓PRELIMINARY FINAL REVISED
AFTER n&Z
1 Coordinate with Atmos for construction/landscaping in Gas Easement.