ST9905-CS060802---
Suzan Taylor -_RE. W Bethel Road Page 1
-- - -
C --- - -
From: <gdkraus@transystems com>
To: <staylor@ci.coppell.tx. us>
Date: 8/2/2006 9'41 45 AM
Subject: RE W Bethel Road
Suzan,
My apologies, I was confusing it with the 5' x 10" boxes. We estimate
about 45 calendar days for the 16" water lowering and box culvert/wing
wall installation assuming the use of high early strength concrete
-----Original Message-----
From Suzan Taylor [mailto:staylor@ci.coppell tx.us]
Sent: Wednesday, August 02, 2006 8'09 AM
To: DL-Garry Kraus
Subject: RE. W Bethel Road
I just need an estimate for the time it will take to construct the 6' x
10' boxes (approximately 70' along the centerline) that cross under
Bethel just east of Loch Lane -the box that is included as part of the
channel improvements. We will only close the road for that section of
improvements.
»> <gdkraus@transystems.com> 8/1/2006 5.24 PM »>
Suzan,
For 2000 feet of cast in place culvert, we estimate a 5 to 6 month
construction time I would think the 16" water lowering could be done
within that same time frame.
-----Original Message-----
From. Suzan Taylor [mailto staylor@ci.coppell.tx.us]
Sent: Tuesday, August 01, 2006 11 40 AM
To: DL-Garry Kraus
Subject: W Bethel Road
Garry
We are going to City Council with an item to close Bethel Road during
the construction of the 4-box culvert at Loch Lane What is your best
estimate on how long the road will need to be closed in order to
construct the cast in place culverts? We will need to include the
time
for lowering the 16-inch water line and relocating the manhole out
from
the culverts.
Thanks
Suzan Taylor