DR9801-LR 981123 GEOTECHNICAL AND I~ ~ E~ I I p
ENVIRONMENTAL CONSULTANTS
REPORT OF FIELD DENSITY TESTS I
Drainage and Paving improvements
Fritz and Freeport Parkway
Coppell, Texas
REPORTED TO: Catellus Development Corporation REPORT NO. 7
4545 Fuller Drive, Suite 100 REPORT DATE: 11-23-98
Irving Texas 75038 REG PROJECT NO. 4998
ATTN: Mr. Robert McCann TECHNICIAN: K. Graham
PAGE: 1 of 2
CONTRACTOR: Wright Construction
1 D-698 Dark brown clay 25.0 94.0
2 D-698 Olive brown clay 23.5 95.5
Eield ;
N~i Dete Location {~;eez)E~el (%)
97 11-06-98 Line A, STA. 8+90 (1) 7.5 89.6 29.6 1 95.3
98 Line A, STA. 8+80 (1) 5.0 90.1 28.9 1 95.9
99 Line A STA. 8+90 (2) 7.5 89.4 29.8 1 95.1
100 Line A, STA. 8+80 (2) 5.0 90.0 28.6 1 95.7
101 Line A, STA. 8+70 4.0 91.7 27.0 2 96.0
102 Line A, STA. 8+60 3.0 91.9 26.8 2 96.2
103 Line A, STA. 8+50 2.0 91.0 27.5 1 96.8
104 Line A, STA. 8+40 1.0 91.3 26.4 1 97.1
105 Line A, STA. 8+30 0.0 91.7 26.1 1 97.5
106 Line A, STA. 9+25 (1) 7.5 90.9 28.4 2 95.2
107 Line A, STA. 9+20 (1) 5.0 91.6 27.8 2 95.9
108 Line A, STA. 9+25 (2) 7.5 91.0 28.3 2 95.3
109 Line A, STA. 9+20 (2) 5.0 91.3 27.2 2 95.6
110 Line A, STA. 9+15 4.0 91.8 26.9 2 96.1
111 Line A, STA. 9+20 3.0 90.5 25.5 1 96.3
112 Line A, STA. 9+25 2.0 90.7 26.9 1 96.5
113 Line A, STA. 9+20 1.0 90.9 26.6 1 96.7
114 Line A, STA. 9+25 0.0 91.5 26.1 1 97.3
115 11-09-98 Line A, STA. 9+65 (1) 6.0 90.9 28.5 2 95.2
116 Line A, STA. 9+60 (1) 3.0 91.4 28.1 2 95.7
117 Line A, STA. 9+65 (2) 6.0 90.7 28.7 2 95.0
118 Line A, STA. 9+60 (2) 3.0 91.1 28.3 2 95.4
119 Line A, STA. 9+60 2.0 89.9 29.6 I 95.6
120 Line A, STA. 9+65 1.0 90.4 28.8 1 96.2
121 Line A, STA. 9+70 0.0 91.0 28.1 1 96.8
122 11-10-98 Line A, STA. 10+30 (1) 6.0 89.5 29.8 1 95.2
123 Line A, STA. 10+25 (1) 3.0 90.1 29.1 1 95.8
124 Line A, STA. 10+30 (2) 6.0 89.7 29.6 1 95.4
125 Line A, STA. 10+25 (2) 3.0 89.9 29.3 1 95.6
126 Line A, STA. 10+20 2.0 90.3 28.4 1 96.1
127 LineA, STA. 10+15 1.0 90.5 27.7 1 96.3 ,
2424 STUTZ DR. · SUITE 400 , DALLAS TX 75235 · TEL [214] 350 5600 · FAX [214] 350 0019
REPORT NO. 7
REPORT DATE: 11-23-98
REG PROJECT NO. 4998
PAGE: 2 of 2
Depth
} Bel~ Field Field
Test' Fi~l~ ~i ~Sity M~i~t~ ~ct~ ~~ti~
NO Date ~ocatlon; ( : :
128 11-10-98 LineA, STA. 10+~0 0.0 90.7 27.3 1 96.5
Comments: Where tested, materials were in compliance with project specifications.
Footnotes: (1) Nodh side of structure.
(2) South side of structure.
Distribution: (1) Catellus Development Corporation/ Submitted by:
Mr. Robe~ McCann
(1) Wright Construction/Mr. Tim Mullikin REED ENGINEERING GROUP, INC.
(1) City of Coppell/Mr. GaKh Campbell
(1) Halff Associates/Mr. Todd Jackson Original Signed By
Ronald F. Reed, P.E.
~sa