SC-Coppell MSW-LR020412FUGRO SOUTH, INC.
�GRO
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484 -8301; Fax (972) 620 -7328
OBSERVATION OF CONCRETE PLACEMENT
CLIENT: Coppell ISD REPORT DATE April 12, 2002
PROJECT: Coppell ISD Service Center, Coppell, Texas PROJECT NO 0701 -2233
DATE PERFORMED: April 10, 2002
General Contractor: CISD
Method of Test Applicable ACI Recommendations and ASTM Standards
Results / Remarks:
Concrete placement observation was
performed at the following location: Tronsformer pad on southside of building
Time placement began:
9:05 a.m.
Time placement ended:
9:40 a.m.
Total cubic yards placed:
10
Slump range (inches):
5 to 5
Slump required (inches):
5
Concrete supplier and plant:
Hanson
Concrete temperature range ( °F):
70 to 70 °F
Strength required (psi /days):
3600/28
Number of cylinders made:
4
Superplasticizer used:
No
James Spriggs
Fugro South Technician
FUGRO SOUTH, INC.
Plant # 22
Reviewed By:
G c
SMH /nl
Distribution: K A Sparks Contractors Inc. — Jim Schooler
K A Sparks Contractors Inc. — Rick McKinney (Fax: 972 - 462 -9320)
City of Coppell - Lee Stone �-
City of Coppell - Garreth Campbell -
Coppell ISD - Mickey Harper
SHW Group — Mike Elmore
SHW Group — Dale Lilljedahl