St Ann Catholic-LR061023REPORT OF REINFORCING & POST TENSION STEEL
Irerracon
OBSERVATION
Consulting Engineers & Scientists
CORRECT
8901 Carpenter Frwy., Suite #100
ITEMS OBSERVED
Dallas, Texas 75247
INCORRECT
(214) 630 -1010
Date of Service 10/23/06 Report No 94061334 0003
Client No 106235 Project No : 94061334
Client: St. Ann Catholic Church Project: St. Catholic Parish
180 Samuel Blvd. ew Addition 180 Samuel Blvd.
Coppell, TX 75019 Coppell, TX
Services. Observe placement of reinforcing for compliance with furnished drawings.
PROJECT DATA
Drawings Utilized C4 l /Pavement Section, dated 08/10/06
Locations /Items Observed- Pavement, Parking Lot, N Side
Test Method. Visual Observation
REPORT OF OBSERVATION
ITEMS OBSERVED
CORRECT
INCORRECT
ITEMS OBSERVED
CORRECT
INCORRECT
ITEMS OBSERVED
CORRECT
INCORRECT
Placing Drawings Approved
X
Length and Shape
X
Column Tie Spacing & Type
Bar and Cable Size
X
Proper Placement
X
Stirrup Spacing & Type
Bar and Cable Grade
X
Property Tied
X
Cables Properly Wrapped
Rebar and Cables Clean
X
Dowel Bars in Place
X
Mechanical Splices
Trash & Debris Removed
X
Proper Supports
X
Lapped Splices
X
Number of Bars and Cables
X
Proper Cover /Clearance
X
Proper Drape of Cables
Discrepancies /Comments. No discrepancies were noted at the time of this observation.
Field Results Report To:
Technician: I. Haynes
Report Distribution:
(1) St Ann Catholic Church (1) Page Southerland Page
(1) City of Coppell TX (1) Technistructures
(1) City of Coppell TX (1) Pacheco Koch Consulting Engineers
Bulent Ethem, P G,
Project Manager
309acs This report is exclusively for the use of the client indicated above and shall not be reproduced without written approval of Terracon.