RE: Budget Estimate for Construction Materials Testing of
MacArthur Blvd. and Cribbs Drive
Drainage Project
DR 06 -01
City of Coppell, Texas
Dear Ms. Taylor,
Lawrence Engineering (LE) is pleased to be selected for the construction materials testing
services for the MacArthur Drive and Cribbs Drive Drainage Project at Coppell, Texas. Our
scope of services is based on our understanding of the project plans and project specifications.
In addition to specific information provided, LE has comprised this project fee schedule based
on an estimated duration of the construction period and typical construction methodology.
Therefore, we request that you carefully review the on -site duration and frequency of testing to
compare with your estimated construction schedule. As you know, our cost is directly
dependent upon the time duration and construction methodology utilized.
Scope of Services
LE proposes to provide the following Construction Materials Testing Services for the MacArthur
Drive and Cribbs Drive Drainage Project as required by the construction drawings and
project specifications.
Concrete and Flowable Fill Placement Inspection
LE will provide a full time concrete technician during concrete and flowable fill placements. This
includes the concrete pavement and any other flowable fill placements. The project
superintendent will be notified of any discrepancies noted during visual observation. Concrete
and flowable fill samples will be taken at appropriate intervals as determined by the project
specifications. Concrete and flowable fill samples will be tested for temperature, entrained air
content, slump, and compressive strength.
12500 Schroeder' Suite B • Dallas, Texas 75243 ' PHN 972 - 497 -9100 • www.lawrenceengineering.com
� 4"wow
MacArthur Blvd. and Cribbs Drive Drainage Project
Ms. Suzan Taylor
P06 -0509
May 15, 2006
Cost Estimate
Presented on Table I attached is our cost estimate for this project. LE's estimates of testing
quantities are based upon material estimates obtained from the Project Construction Drawings
and assumed accepted industry standards for items not specified. We believe that our total cost
estimate is realistic for this project; however, this estimate may be increased or decreased
depending upon the actual project progress and the conditions encountered during project
construction. These are estimates. Consequently, billings only for services rendered will be
based primarily upon the unit rates presented in Table I.
An invoice for services performed during each month will be sent within the first 10 days of the
following month. Payment for our services will be due within 30 days of receipt of invoice.
Schedule
Lawrence Engineering is prepared to begin work immediately upon notification to proceed from
the project representative. We are prepared to respond to your needs with due diligence in a
timely fashion, as well as establish a level of communication which facilitates progress.
Acceptance
Lawrence Engineering is committed to, and capable of, providing the required materials
engineering and testing services that are necessary for timely and professional project
performance. LE's engineering technicians are either certified by the American Concrete
Institute and National Institute for Certification in Engineering Technologies (NICET) or enrolled
in certification programs. Lawrence Engineering is regularly inspected by the Cement and
Concrete Reference laboratory (CCRL), is accredited by American Association of State
Highway and Transportation Official (AASTHO), and is certified by North Central Texas Region
Certification Agency as Disadvantage Business Enterprise (DBE).
We thank you for your consideration of this proposal and look forward to serving your
professional needs on this project. If you require further information, please do not hesitate to
contact us.
Sincerely,
Lawrence Engineering
Rolando Ramirez
Project Manager
Lawrence Engineering
-/� %.Z "l
Gary D. Dry
CMT Manager
12500 Schroeder • Suite B • Dallas, Texas 75243 • PHN 972 -497 -9100 • www.lawrenceengineering.com
Table I
Construction Materials Testing for
MacArthur Blvd. and Cribbs Dr.
Drainage Project
DR 06 -01
City of Coppell
Lawrence Engineering Proposal No. P06 -0509
15- May -06
NOTES:
1. Overtime and retest confirmation will be invoiced to project General Contractor. (If required)
Overtime rates of 1.5 times the regular hourly rate will be charged for hours worked on the project outside
the normal working hours of 7:00 am to 5:00 p.m., over eight hours per day, excluding travel time to and
from the jobsite, Monday through Friday. Services performed on Saturday and Sunday will be billed at
1.5 times the regular rate. Services performed on recognized holidays will be billed at 2.0 times the
regular hourly rate.
2. All laboratory test fees are F.O.B our laboratory; additional charge for sample pickup may apply.
3. Any additional tests will be billed on a hourly rate and charged at the applicable rate, portal to portal.
4. Additional test not specified in this proposal will be quoted upon request.
Estimated
I
Unit
I
Estimated
Service Description
Quantity
Units
Price
Cost
Concrete Placement Inspection
Concrete Technician - Portal to Portal (min. 2 hours per trip)
20
Hours
$34.00
$680.00
Compressive Strength Test Cylinders
32
Each
$14.50
$464.00
Trip Charge - Vehicle Usage
8
Each
$25.00
$200.00
Subtotal
$1,344.00
Proiect Management
Project Manager - General Project Coordination /Report Review
2
Hours
$65.00
$130.00
Subtotal
$130.00
Estimated Total Cost
1
$1,474.00
NOTES:
1. Overtime and retest confirmation will be invoiced to project General Contractor. (If required)
Overtime rates of 1.5 times the regular hourly rate will be charged for hours worked on the project outside
the normal working hours of 7:00 am to 5:00 p.m., over eight hours per day, excluding travel time to and
from the jobsite, Monday through Friday. Services performed on Saturday and Sunday will be billed at
1.5 times the regular rate. Services performed on recognized holidays will be billed at 2.0 times the
regular hourly rate.
2. All laboratory test fees are F.O.B our laboratory; additional charge for sample pickup may apply.
3. Any additional tests will be billed on a hourly rate and charged at the applicable rate, portal to portal.
4. Additional test not specified in this proposal will be quoted upon request.
LAWRENCE ENGINEERING
Environmental - Geotechnical • Material Testing
PROPOSAL ACCEPTANCE AGREEMENT
Description of Services: Construction Materials Testing
Project Name: MacArthur Blvd. and Cribbs Drive Drainage Improvements
Project Location: Coppell, Texas
LE Proposal #: P06 -0509
APPROVAL AND PAYMENT OF CHARGES. Fees will be billed to the account of, and invoices will be mailed to:
Firm: City of Coppell
Attention: Kenneth M. Griffin, P.E., Dir. of Engineering
Address: 255 Parkway Blvd.
City: Coppell State: TX Zip: 75019
Telephone 972 304CL3686 �2 30 W —70 4 1
Proposal Accepted By:
Title:
Date Accepted:
PAYMENT TERMS: Payable in accordance with the attached agreement(s). Invoices for completed work will be
issued every month for continuous or extended projects unless otherwise mutually agreed upon in writing.
PROPERTY OWNER IDENTIFICATION: (If other than above)
Name:
Address:
City:
Telephone_
SPECIAL PROVISIONS:
State:
Fax:
Zip:
Please note that Lawrence Engineering reserves the right to withhold all reports until such time as Lawrence Engineering
receives a signed Proposal Acceptance Agreement or other written authorization referencing this agreement in its entirety
This AGREEMENT, together with Lawrence Engineering's Proposal, Unit Fee Schedule and the attached agreement(s), as
indicated below, constitutes the entire agreement between the client and Lawrence Engineering and supersedes all prior
written or verbal understandings.
• Professional Services Agreement
• Agreement for Materials Testing Services