Gateway BP(1.6)-LR061115REPORT OF REINFORCING STEEL OBSERVATION l~i~rr~con
Consultlnp Enplneers E SGentlsts
8901 Carpenter Fnvy., Suite #100
Dallas, Texas 75247
(2141630-IOIO
Date of Service: 11/15/06
Client No.: 47876
Client: ProLogis
2310 LBJ Freeway Ste 200
Dallas, TX 75234
Report No.: 94061163.0159
Project No.: 94061163
Project: Freeport Corporate Ctr. Bldg. 6
Freeway Pkwy & Gateway
Coppell, TX
Services: Observe placement of reinforcing for compliance with furnished drawings.
PROJECT DATA
Drawings Utilized: Ramp Sheet 54.2/Detail #2, dated 05/22/06; Pavement C1.11, dated 06/01/06
Locations/items Observed: Pavement, W of Building and Ramp NW of Building
Test Method: Visual Observation
REPORT OF OBSERVATION
ITEMS OBSERVED CORREC7 INCORRECT ITEMS OBSERVED CORRECT INCORRECT ITEMS OBSERVED CORRECT INCORRECT
Placing Drawings Approved X Bar Length and Shape X Column Tie Spacing & Type
Bar Size X Proper Bar Placement X Stirrup Spacing & Type
Bar Grade X Properly Tied X Welded Splices
Rebar Clean X Dowel Bars in Place X Mechanical Splices
Trash 8 Debris Removed X Proper Bar Supports X Lapped Splices X
Number of Bars X Proper CoverlClearance X
Discrepancieslcomments: No discrepancies were noted at the time of this observation.
Field Results Report To:
Technician: J.A. Martinez
Report Distribution:
(1) ProLogis
(1) City of Coppell TX
(1) City of Coppell TX
(1) Haynes Whaley Assoc Inc
(1) Meinhardt 8r Assoc Architects Pt
(1) Jordan Construction Services
(1}Meinhardt & Assoc Architects PLLC
Robert ay, S.E.T.
Seni roject Manager
309acs This report is exclusively for the use of the client indicated above and shall not be reproduced without written approval of Terracon.