Coppell Trade 2-LR061107/! ~~.
f
FARt~O CONSiTLTANTB, INC.
WATER PRESSURE INJECTION
OBSERVATION REPORT
Client: Holt Lunsford Commercial
Project: Coppell Trade Center Building D
Coppell, Texas
Injection Contractor: Mcfadden & Miller
11440 Reeder Rd. • Dallas, Texas 75229
Tel. 214-352-4100 Fax. 214-352-4811
Page 1 of 1
Date of Service: 11/07/06
Project No: M06-1165
Location: Building pad -west half
Area injected previously: Approximately 11, 000 square feet of 2nd pass
Area injected (on this day): Approximately 16,800 square feet of 2°d pass
Area injected (to date): Approximately 27,800 square feet of 2nd pass
Gallons of Water used: 68,000
Surfactant Used: lgallon / 3,500 gallons of water
Injection Pressure (psi): 80
Injection Probe Spacing (feet): 5
Injected Depth Interval (in.) until refusal: 5
Total Depth of Injection (feet): 12
Remarks:
Time
Start 7:00 a.m. / 2:00 p.m.
End 9:00 a.m. / 3:00 p.m.
S ecified Requirements
as per manufacturer
50 psi-100psi
5 feet (max.)
12 inches
12 feet
Water Meter Reading
8819600
8887600
Technician: William Youngstrom
Distribution: Holt Lansford Commercial -Ken Newman
Mcfadden & Miller- Jon Jacobson
City of Coppell -Lee Stone
Checked by:
LIMITATIONS: This report presents test results (at particular locations noted) based on data obtained from specific samp]es selected for testing. Fargo Consultants, Inc. assumes no
responsibility for variation in quality, performance, feature or conditions beyond its control. This report is for the exclusive use of the person(s) to whom it is addressed
and may not be reproduced except in full without the written approval of Fargo Consultants, Inc.