FARGO CONSULTANTS, INC.
11440 Reeder Rd. • Dallas, Texas 75229
Tel. 214-352-4100 Fax. 214-352-4811
LIME MODIFIED SOIL PULVERIZATION REPORT
Tested For: Holt Lunsford Commercial Date Performed: 11/16/06
Project Name: Coppell Trade Center Building D FCI Project No.: M06-1165
Coppell, Texas
Contractor: Mcfadden and Miller
LIME TREATED SOIL PULVERIZATION TEST RESULTS
Percent Passing Percent Passing
Location 1 3/4" Sieve #4 Sieve
1 Building pad, 30'N by 30'W from SE building corner 100 63.2
2 Building pad, 50'N by 15'W from SE building corner 100 65.6
3 Building pad, 10'S by 45'W from NE building corner 100 63.1
4 Building pad, 15'N by 200'W from SE building corner 100 62.1
5 Building pad, 50'N by 190' W from SE building corner 100 63.7
6 Building pad, 25' S by 215'W from NE building corner 100 62 3
7 Building pad, 10' S by 340' W from NE building corner 100 57 2 *
8 Building pad, 60'S by 380'W from NE building corner 100 59.2*
9 Buildirg pad, 20'N by 375'W from SE building corner 100 55.9*
10 Retest for test number 7 same report 100 63.2
11 Retest for test number 8 same report 100 60.9
12 Retest for test number 9 same report 100 61.5
Project Requirements: Minimum 100% Minimum 60%
Remarks: *Test result does not comply with project requirements
Technician: Gary Moore, C.E.T.
Respectfully Submitted,
Fargo Consultants, Inc.
Checked By: ~~
Distribution: Holt Lansford Commercial -Ken Newman
Mcfadden & Miller -Jon Jacobson
City of Coppell -Lee Stone