SW0001-MP011114 I RIVERCHASE SIDEWALK
SW 00-01
PACHECO KOCH ENGINEERING
Qtr 3, 2001 Qtr 4, 2001
ID Task Name Jun Jul Aug Sep Oct j Nov
1 DESIGN PHASE
2 Design 1_ J
3 Advertisement
4 Bid Opening
5 City Council
— 6 - RIGHT -OF -WAY
7 City of Irvin
8 Response Received 1 A 10110
9 Dallas Water Utilities ', 1:::::::::E:::::::::1
10 TXU Electric t ..:................... :.... � ]
11 Response Received . 10/09
12 Lot 11 River Ridge Add.
13 HOA River Ridge Add.
14 CONSTRUCTION
15 Notice to Proceed
16 Construction
Project: SW 00-01 Task 1 I Milestone . Summar IFININ■ Deadline
Date: Wed 11/14/01
Page 1
RIVERCHASE SIDEWALK
SW 0001
PACHECO KOCH ENGINEERING
2 Design
May need to be redesigned to avoid conflict with TXU transmission lines. Working with TXU to resolve Issue.
8 Response Received
Requested that portion of sidewalk within easement be redesigned.
11 Response Received
Denied request for use of right -of -way.
Page 2