SW0001-MP011024 RIVERCHASE SIDEWALK
SW 00-01
PACHECO KOCH ENGINEERING
Qtr 3, 2001 1 Qtr 4, 2001
ID Task Name Jun Jul Aug Sep Oct Nov
1 DESIGN PHASE
2 Design E :.......:::...
3 Advertisement
4 Bid Opening
5 City Council
6 RIGHT -OF -WAY
7 City of Irving 1-
8 Response Received . 10/10
9 Dallas Water Utilities
10 TXU Electric
11 Response Received . 10109
12 Lot 11 River Ridge Add.
13 HOA River Ridge Add.
14 CONSTRUCTION
15 Notice to Proceed
16 Construction
Project: SW 00-01 Task 1 1 Milestone . Summary Deadline 4,
Date: Wed 10/24/01
Page 1
RIVERCHASE SIDEWALK
SW OD-M
PACHECO KOCH ENGINEERING
2 Design
►Nsy need to be redesigned to avoid oonfllct with TXU taremission Ikm. Wkxiang with TXU to resobe issue.
I Response Received
Requested that portion of sidewalk within easement be redesigned.
11 Response Received
Denied request for use of right -of -way.
Page 2