SW0001-MP010927 RIVERCHASE SIDEWALK SW 00 -01 PACHECO KOCH ENGINEERING Qtr 3, 2001 Qtr 4, 2001 Qtr 1, 2002 ID Task Name Duration Start Finish Predecessors Jun Jul Aug ; Sep Oct Nov Dec Jan Feb Mar 1 I DESIGN PHASE 80 days Tue 07124/01 Tue 11/13/01 2 Design 50 days Tue 07/24/01 Mon 10/01 /01 h - = = =;J— 3 Advertisement 12 days Fri 10/12/01 Mon 10/29/01 2 - -- 4 Bid Opening 0 days Tue 10/30/01 Tue 10/30/01 3 A 10/30 5 City Council 0 days Tue 11/13/01 Tue 11/13/01 ; , 11/13 6 RIGHT 45 days Tue 07/24/01 Mon 09/24/01 7 City of Irving 9 days Wed 09/12/01 Mon 09/24/01 I 8 Dallas Water Utilities 9 days Wed 09/12/01 Mon 09/24/01 O 9 TXU Electric 9 days Wed 09/12/01 Mon 09/24/01 O 10 — Lot 11 River Ridge Add. 0 days Tue 07/24/01 Tue 07/24/01 11 CONSTRUCTION 52 days Fri 11/30/01 Mon 02/11/02 gpMEMMINIV L 12 Notice to Proceed O days Fri 11/30/01 Fri 11/30/01 A41/30 13 Construction 60 edays Thu 12/13/01 Mon 02/11/02 12FS +10 days - == :3 Project: SW 00 -01 Task I I Milestone . Summary Deadline Date: Thu 09/27/01 Page 1