Loading...
Town Center L1B2-CS000120 (3)1�f January 20, 2000 Mr. Doug Talley, Sr. Project Manager Hill & Wilkinson, Inc. 11969 Plano Rd., Suite 190 Dallas, Texas 75243 -5486 P.O. Box 478 Coppell, Texas 75019 972 - 462 -0022 4lle,o RE: Town Center Addition, Lot 1, Block 2 (Tom Thumb) Final Walk -thru Dear Doug: 0 (A " " l Please be advised that a walk -thro has been scheduled for Friday, January 21, 2000 at 9:00 a.m. for the water, sanitary sew cilities in the referenced project. Please ensure that all facilities are clean and accessible at that time and that contractor's representatives are present to assist with the inspection. Your cooperation in this effort is greatly appreciated. If you should have any questions, please call 972 -304 -3685 at your earliest convenience. Sincerely, �1 I �T ��, = f "he City With A Beautiful Future 1 .0. BOX 478 ;OPPELL,TEXAS 75019 cc: Lee Stone, Commercial Inspector Calhar Construction (fax: 972 - 235 -6377) Mark Morris, North American Prop. - Southwest (fax: 972 - 866 -9888) 972 304 3547 011;?4100 10:23 CITY OF COPPELL 4 CITY OF COPPELL NO.116 i MEMORANDUM FROM THE DEPARTMENT OF PUBLIC WORKS To: Garreth Campbell, Constru:dou Inspector Engineering From: Danny Hightower, Utiiitks Division Public Works Date: January 21, 2000 RE: Walk thru Tom Thumb 1121/00 1. Manhole chimney seals need to be raised. 2. Two inch double checks-ball valves need caps. 3. Vault needs caps and plugs on the ball valves. 4. Reset the blocking under wheel valves in vault. S. Need a hinge on top of vault. 6. Irrigation meter needs a 2" curb stop. r. CRY OF COPPELL PUSUG WORKS DEPARTAMPVT