SC-Coppell MSN-LR 971010FUGRO- McCLELLAND (SOU THWEST), INC. o f 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484 -8301; Fax (972) 620 -7328 OBSERVATION OF CONCRETE PLACEMENT CLIENT: Coppell ISD REPORT DATE: October 10, 1997 PROJECT: Coppell Middle School North Sitework, Coppell, Texas PROJECT NO: 0771 -2094 DATE PERFORMED: October 1, 1997 General Contractor: K.A. Sparks Contractors, Inc. Method of Test: Applicable ACI Recommendations and ASTM Standards Results / Remarks: Concrete placement observation was performed at the following location: Perimeter Road Time placement began: Time placement ended: Total cubic yards placed: Slump range (inches): Slump required (inches): Concrete supplier and plant: Concrete temperature range ( °F): Strength required (psi /days): Number of cylinders made: Superplasticizer used: Bob Shea Fugro - McClelland Technician 7:00 A.M. 5:00 P.M. 500 3 -5.5 5.0 Pioneer 88 -94 °F 4000/28 40 No FUGRO- McCLELLAND (SOUTHWEST), INC. Checked By: SMH /mv Distribution: Coppell ISD - Mickey Harper City of Coppell - Garreth Campbell K A Sparks Contractors, Inc. - E. J. Williams (2) SHW Group - Joe Craddock K A Sparks Contractors, Inc. - Jim Schooler SHW Group - Mike Elmore �GRO FUGRO- McCLELLAND (SOUTHWEST), INC. 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484 -8301; Fax (972) 620 -7328 OBSERVATION OF CONCRETE PLACEMENT CLIENT: Coppell ISD REPORT DATE: October 10 1997 PROJECT Coppell Middle School North Sitework, Coppell, Texas PROJECT NO 0771 - 2094 DATE PERFORMED: September 30,1997 General Contractor: K.A. Sparks Contractors, Inc. Method of Test Applicable ACI Recommendations and ASTM Standards Results / Remarks: Concrete placement observation was performed at the Fire lane southwest parking area following location: Time placement began: Time placement ended: Total cubic yards placed: Slump range (inches): Slump required (inches): Concrete supplier and plant: Concrete temperature range ( °F): Strength required (psi /days): Number of cylinders made: Superplasticizer used: Burl Cooper Fugro - McClelland Technician SMH /mv Distribution: Coppell ISD - Mickey Harper K A Sparks Contractors, Inc. K A Sparks Contractors, Inc. 8:00 A.M. 12:00 P.M. 300 4 -5 5 Pioneer 78 -89 °F 3500/28 24 No FUGRO- McCLELLAND (SOUTHWEST), INC. Checked By: City of Coppell - Garreth Campbell - E. J. Williams (2) SHW Group - Joe Craddock - Jim Schooler SHW Group - Mike Elmore FUGRO- McCLELLAND (SOUTHWEST), INC. �GRO 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484 -8301; Fax (972) 620 -7328 COMPRESSIVE STRENGTH OF CONCRETE REPORT CLIENT Coppell ISD Report Date October 10, 1997 PROJECT Coppell Middle School North Sitework Coppell, Texas Project No.: 0771 -2094 SAMPLE DATE: September 29 1997 CONTRACTOR: TICKET NO.: AMBIENT TEMP. (°F): CONCRETE TEMP. ( °F) (ASTM C -1064) TIME BATCHED: TIME SAMPLED: WEATHER CONDITION: LOCATION OF PLACEMENT: Tiseo Paving 484591 CONCRETE SUPPLIER: Pioneer 82 PLANT /TRUCK: 27/121 88 MIX ID NUMBER: 9351 9:10 am AIR ( % ) (ASTM C -231) LOAD 9:35 am WATER ADDED (gal): 0 Clear SLUMP (in .) (ASTM C -143) : 41/2 Paving: Eastbound Natches Trace Drive, station 5 +00 CONCRETE CYLINDER COMPRESSIVE' STRENGTH TESTS Standard 6" x 12 28.27 square inches TOTAL COMPRESSIVE REQUIRED COMPRESSIVE CYLINDER AGE DATE LOAD STRENGTH STRENGTH NUMBER (days) TESTED (pounds) (psi) (psi) CNS 1 7 10/06/97 84000 2971 3000/28 days CNS 2 28 10/27/97 CNS 3 28 10/27/97 CNS 4 Hold Fracture mode is (A) unless otherwise noted Specifications: Making & ASTM C -31 Testing ASTM C -143, Types of 0 Curing: Methods: ASTM C -39 Fracture: A® B C D REMARKS: Technician: Mark Strittmatter FUGRO- McCLELLAND (SOUTHWEST), INC. Checked By: SMH /rm Distribution: Coppell ISO - Mickey Harper City of Coppell - Garreth Campbell K A Sparks Contractors, Inc. - E. J. Williams (2) SHW Group - Joe Craddock K A Sparks Contractors, Inc. - Jim Schooler SHW Group - Mike Elmore FUGRO-McCLELLAND (SO UTHWEST), INC. �GRO 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484 -8301; Fax (972) 620 -7328 COMPRESSIVE STRENGTH OF CONCRETE REPORT CLIENT Coppell ISD Report Date October 10, 1997 PROJECT Coppell Middle School North Sitework Coppell, Texas Project No .: 0771 -2094 SAMPLE DATE: September 29, 1997 CONTRACTOR: TICKET NO.: AMBIENT TEMP. (°F): CONCRETE TEMP. ( °F) (ASTM C -1064) TIME BATCHED: TIME SAMPLED: WEATHER CONDITION: LOCATION OF PLACEMENT: Tiseo Paving 484613 CONCRETE SUPPLIER: Pioneer 85 PLANT /TRUCK: 27/Tiseo 88 MIX ID NUMBER: 9351 10:40 am AIR ( % ) (ASTM C -231) : LOAD 11:00 am WATER ADDED (gal): 0 Clear SLUMP (in.) (ASTM C -143) : 51/2 Paving: Eastbound Natches Trace Drive, station 8 +00 CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS Standard 6" x 12 28.27 square' inches TOTAL COMPRESSIVE REQUIRED COMPRESSIVE CYLINDER AGE DATE LOAD STRENGTH STRENGTH NUMBER (days) TESTED (pounds) (psi) (psi) CNS 5 7 10/06/97 80000 2829 3000/28 days CNS 6 28 1 10127/97 CNS 7 28 10/27/97 CNS 8 Hold Fracture mode is (A) unless otherwise noted Specifications: ? Making & ASTM C -31 Testing ASTM C -143, Types of Curing: Methods: ASTM C -39 Fracture: A® B C D REMARKS: Technician: Mark Strittmatter FUGRO MCCLELLAND (SOUTHWEST), INC. Checked By: SMH /rm Distribution: Coppell ISD - Mickey Harper City of Coppell - Garreth Campbell K A Sparks Contractors, Inc. - E. J. Williams (2) SHW Group - Joe Craddock K A Sparks Contractors, Inc. - Jim Schooler SHW Group - Mike Elmore