SC-Coppell MSN-LR 970910FUGRO- McCLELLAND (SOUTHWEST), INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484 -8301; Fax (972) 620 -7328
LIME STABILIZED SOIL PULVERIZATION REPORT
CLIENT: Coppell ISD REPORT DATE: September 10, 1997
PROJECT Coppell Middle School North Sitework, Coppell, Texas PROJECT NO: 0771 -2094
DATE PERFORMED: September 5, 1997
Contractors on Site: K. A. Sparks Contractors Inc.
Remarks Pulverization /Gradation tests were performed. Locations and results are listed below:
LIME STABILIZED SOIL PULVERIZATION TEST RESULTS
Location
Percent Passing Percent Passing
1 3/4" Sieve #4 Sieve
1 West parking area approximately 300
100
62
feet north, 50 feet west of southwest
corner of building
2 West parking area approximately 200
100
60
feet north, 150 feet west of southwest
comer of building
3 West parking area approximately 150
100
61
feet north, 100 feet west of southwest
comer of building
4 West parking area approximately 350
100
68
feet north, 250 feet west of southwest
comer of building
5 West parking area approximately 400
100
70
feet north, 300 feet west of southwest
corner of building
6 West Fire lane approximately 50 feet
100
65
north, 25 feet west of southwest corner
of building
7 West Fire lane approximately 150 feet
100
63
north, 25 feet west of southwest corner
of building
8 West Fire lane approximately 200 feet
100
69
north, 25 feet west of southwest corner
of building
Project Requirements: Minimum 100% Minimum 60%
SPECIFICATIONS: SDHPT Item 260.4 (1972) #4 Sieve
SDHPT Item 260.4 (1982) 3/4" Sieve
Burl Cooper
Fugro - McClelland Technician FUGRO McCLELLAND (SOUTHWEST), INC.
Checked By
SMH /mv
Distribution: Coppell ISD - Mickey Harper City of Coppell - Garreth Campbell
K A Sparks Contractors, Inc. - E. J. Williams (2) SHW Group - Joe Craddock
K A Sparks Contractors, Inc. - Jim Schooler SHW Group - Mike Elmore