SC-Coppell MSN-LR 970905a FUGRO- McCLELLAND (SOUTHWEST), INC. 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484 -8301; Fax (972) 620 -7328 OBSERVATION OF CONCRETE PLACEMENT CLIENT: Coppell ISD REPORT DATE: September 5, 1997 PROJECT: Coppell Middle School North, Coppell, Texas PROJECT NO: 0771 -2091 DATE PERFORMED: August 28 1997 General Contractor: K A Sparks Method of Test: Applicable ACI Recommendations and ASTM Standards Results / Remarks: Concrete placement observation was performed at the Grade beams, area C, 27 through 38, B through R following location: Time placement began: 2:30 P.M. Time placement ended: 7:00 P.M. Total cubic yards placed: 130 Slump range (inches): 5 Slump required (inches): 5 Concrete supplier and plant: Pioneer / 74 Concrete temperature range ( °F): 84 - 86 °F Strength required (psi /days): 3500/28 Number of cylinders made: 12 Superplasticizer used: No Nabil Mikhail Fugro - McClelland Technician FUGRO- McCLELLAND (SOUTHWEST), INC. Checked By: SMH /mv Distribution: Coppell ISD - Mickey Harper City of Coppell - Garreth Campbell — K A Sparks Contractors, Inc. - E. J. Williams (2) SHW Group - Joe Craddock K A Sparks Contractors, Inc. - Jim Schooler SHW Group - Mike Elmore �GRO FUGRO- McCLELLAND (SOUTHWEST), INC. '�—`- 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484 -8301; Fax (972) 620 -7328 COMPRESSIVE STRENGTH OF CONCRETE REPORT CLIENT Coppell ISD Report Date September 5, 1997 PROJECT Coppell Elementary School #10, Coppell, Texas Project No .: 0771 - 2089 r SAMPLE DATE: August 27, 1997 CONTRACTOR: TICKET NO.: AMBIENT TEMP. ( °F): CONCRETE TEMP. ( °F) (ASTM C -1064) TIME BATCHED: TIME SAMPLED: WEATHER CONDITION: LOCATION OF PLACEMENT: K. A. Sparks / Cortez 448956 CONCRETE SUPPLIER: Pioneer 84 PLANTITRUCK: 74 85 MIX ID NUMBER: 9337 COMPRESSIVE AIR ( %) (ASTM C -231) CYLINDER 11:00 WATER ADDED (gal): LOAD clear SLUMP (in.) (ASTM C -143) : 43/4 Slab on grade, area C -2, 10 feet West, 28 feet North of Southeast corner. (psi) (psi) REMARKS: Technician: Scott Rogers FUGRO- McCLELLAND (SOUTHWEST), INC. Checked By: SMH /hb Distribution: Coppell ISD - Mickey Harper City of Coppell - Garreth Campbell K A Sparks Contractors, Inc. - E. J. Williams (2) SHW Group - Joe Craddock K A Sparks Contractors, Inc. - Jim Schooler SHW Group - Mike Elmore CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS Standard 6" x 12 ", 28.27 square inches TOTAL COMPRESSIVE REQUIRED COMPRESSIVE CYLINDER AGE DATE LOAD STRENGTH STRENGTH NUMBER (days) TESTED (pounds) (psi) (psi) CES 215 7 9/3/97 95000 3360 3000/28 days CES 216 28 9/24/97 CES 217 28 9124197 CES 218 Hold Fracture mode is (A) unless otherwise noted Specifications: Making & ASTM C -31 Testing ASTM C- 143, '. Types of D Curing: I Methods: ASTM C -39 Fracture: A® B® C REMARKS: Technician: Scott Rogers FUGRO- McCLELLAND (SOUTHWEST), INC. Checked By: SMH /hb Distribution: Coppell ISD - Mickey Harper City of Coppell - Garreth Campbell K A Sparks Contractors, Inc. - E. J. Williams (2) SHW Group - Joe Craddock K A Sparks Contractors, Inc. - Jim Schooler SHW Group - Mike Elmore GRID FUGRO- McCLELLAND (SOUTHWEST), INC. --- 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484 -8301; Fax (972) 620 -7328 COMPRESSIVE STRENGTH OF CONCRETE REPORT CLIENT: Coppell ISD Report Date: September 5, 1997 PROJECT: Coppell Middle School North, Coppell, Texas Project No.: 0771 -2091 SAMPLE DATE: August 28, 1997 CONTRACTOR: TICKET NO.: AMBIENT TEMP. (°F): CONCRETE TEMP. (°F) (ASTM C- 1064): TIME BATCHED: TIME SAMPLED: WEATHER CONDITION: LOCATION OF PLACEMENT: K A Sparks / Cortez 449080 CONCRETE SUPPLIER: Pioneer 90 PLANTITRUCK: 74 -751 84 MIX ID NUMBER: 9337 5:26 p.m AIR ( %) (ASTM C -231) : 6:00 p.m WATER ADDED (gal): Sunny SLUMP (in.) (ASTM C -143) : 5 Grade beams area C, M through B at 33 through 36 CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS' Standard 6" x 12 ", 28.27 square inches TOTAL COMPRESSIVE REQUIRED COMPRESSIVE CYLINDER AGE DATE LOAD STRENGTH STRENGTH NUMBER (days) TESTED (pounds) (psi) (psi) CMN 291 7 9/4/97 95000 3360 3500/28 days CMN 292 28 9/25/97 CMN 293 28 9/25/97 CMN 294 Hold Fracture mode is (A) unless otherwise noted Specifications: Making & ASTM C -31 Testing ASTM C -143, Types of Fracture: Curing: Methods: ASTM C -39 A® B® C D REMARKS: Technician: Nabil Mikhail FUGRO- McCLELLAND (SOUTHWEST), INC. Checked SMH /hb Distribution: Coppell ISD - Mickey Harper City of Coppell - Garreth Campbell K A Sparks Contractors, Inc. - E. J. Williams (2) SHW Group - Joe Craddock K A Sparks Contractors, Inc. - Jim Schooier SHW Group - Mike Elmore FUGRO- McCLELLAND (SOUTHW INC. �GRO a l 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484 -8301; Fax (972) 620 -7328 COMPRESSIVE STRENGTH OF CONCRETE REPORT CLIENT: Coppell ISD Report Date: September 5, 1997 PROJECT Coppell Middle School North, Coppell, Texas Project NO.: 0771 -2091 SAMPLE DATE: August 28, 1997 CONTRACTOR: TICKET NO.: AMBIENT TEMP. (°F): CONCRETE TEMP. (°F) (ASTM C -1064) TIME BATCHED: TIME SAMPLED: WEATHER CONDITION: LOCATION OF PLACEMENT: K A Sparks / Cortez 449072 CONCRETE SUPPLIER: Pioneer 92 PLANT/TRUCK: 74 -744 84 MIX ID NUMBER: 9337 4:15 p.m AIR ( % ) (ASTM C -231) : 5:00 p.m WATER ADDED (gal): Sunny SLUMP (in.) (ASTM C -143) : 5 1/2 Grade beams area C, R through E at 32 through 33 CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS Standard 6" x 12 ", 28.27 square inches TOTAL COMPRESSIVE REQUIRED COMPRESSIVE CYLINDER AGE DATE LOAD STRENGTH STRENGTH NUMBER (days) TESTED (pounds) (psi) (psi) CMN 287 7 9/4/97 103000 3643 3500/28 days CMN 288 28 9/25/97 CMN 289 28 9/25/97 CMN 290 Hold Fracture mode is (A) unless otherwise noted Specifications: Making & ASTM C -31 Testing ASTM C- 143, Types of Curing: Methods: ASTM C -39 Fracture: A® B® C D REMARKS: Technician: Nabil Mikhail FUGRO- McCLELLAND (SOUTHWEST), INC. Checked 13 — i SMH /hb Distribution: Coppell ISD - Mickey Harper City of Coppell - Garreth Campbell K A Sparks Contractors, Inc. - E. J. Williams (2) SHW Group - Joe Craddock K A Sparks Contractors, Inc. - Jim Schooler SHW Group - Mike Elmore FUGRO- McCLELLAND (SOUTHWEST), INC. 2880 Virgo Lane; Dallas, Texas 75229 Ph (972) 484 -8301; Fax (972) 620 -7328 COMPRESSIVE STRENGTH OF CONCRETE REPORT CLIENT: Coppell ISO Report Date: September 5, 1997 PROJECT: Coppell Middle School North, Coppell, Texas Project No.: 0771 -2091 SAMPLE DATE: August 28, 1997 CONTRACTOR: TICKET NO.: AMBIENT TEMP. (°F): CONCRETE TEMP. (°F) (ASTM C -1064) TIME BATCHED: TIME SAMPLED: WEATHER CONDITION: LOCATION OF PLACEMENT: K A Sparks / Cortez 449066 CONCRETE SUPPLIER: Pioneer 90 PLANTITRUCK: 74194 86 MIX ID NUMBER: 9337 2:55 p.m AIR ( %) (ASTM C -231) : LOAD 3:56 p.m WATER ADDED (gal): 5 Sunny SLUMP (in.) (ASTM C -143) : 5 Grade beams area C, CA - 27 through CA - 32 and T through J at 27 through 32 7 9/4/97 CONCRETE CYLINDER COMPRESSIVE' STRENGTH TESTS Standard 6 "' x 12 ", 28.27 square inches TOTAL COMPRESSIVE REQUIRED COMPRESSIVE CYLINDER AGE DATE LOAD STRENGTH STRENGTH NUMBER (days) TESTED (pounds) (psi) (psi) CMN 283 7 9/4/97 90000 3183 3500/28 days CMN 284 28 9/25/97 CMN 285 28 9/25/97 CMN 286 Hold Fracture mode is (A) unless otherwise noted Specifications: Making & ASTM C -31 Testing ASTM C- 143, '. Types of :Fracture: Curing: :Methods: ASTM C -39 A® B® C D REMARKS: Technician: Nabil Mikhail FUGRO- McCLELLAND (SOUTHWEST), INC. Checked By: SMH /hb Distribution: Coppell ISO - Mickey Harper K A Sparks Contractors, Inc. K A Sparks Contractors, Inc. City of Coppell - Garreth Campbell - E. J. Williams (2) SHW Group - Joe Craddock - Jim Schooler SHW Group - Mike Elmore