DR8902-CS 891023 GINN, INC. CONSULTING ENGINEERS
October 23, 1989
Mr. Rick Bennett
SYB Construction Co., Inc.
P.O. Box 13614
Arlington, TX 76094-0614
Re: Bethel/Pelican Drainage Improvements
Certificate of Completion
Dear Mr. Bennett:
The work to which this certificate applies has been inspected by
authorized representatives of the Engineer and City of Coppell
personnel and that work is hereby declared to be complete in
accordance with the Contract Documents as of October 20, 1989.
Executed by Engineer on ~~ ~ , 1989.
Ginn, Inc. Consulting Engineers
Contractor accepts this Certificate of Completion as of October
20, 1989, on this day of , 1989.
SYB Construction Co., Inc.
By:
17103 Preston Road · Suite 100 · LB 118 · Dallas, Texas 75248 · Phone 214/248-4900
Owner accepts the project as complete as of October 20, 1989 on
this day of , 1989, and will
assume full possession of the project immediately.
city of Coppell
By:
City Engineer
Please sign and return all copies to us for further execution and
distribution. After execution of this document by the Owner, we
will return a copy to you.
You may proceed with final contract close-out documents in
accordance with Section 01700 of the Specifications including
Waiver of Lien, Release from Bonding Company, certificate that
all accounts have been paid, letter of warranty for a period of
one year and final payment request.
Should you have any questions, please contact us.
Sincerely,
Gabe Favre
cc: Russell Doyle, P.E.
Steve Goram
Per Birdsall
Larry Davis
H. Wayne Ginn, P.E.
Randy Fleming
File 89420