Loading...
ST9401-CN 981020October 20, 1998 Mr. Garreth Campbell City of Coppell Engineering Dept. P.O. Box 478 Coppell, Texas 75019 RE: Denton Tap Road Dear Garreth: d" 4 p-rwe- VX'n Ca'nQA 11- to `.,)& The redesign of the bridge railing on this project involves the following changes in costs: Delete the following from the contract: 19. Furnish and install special bridge rails 1,4871-F $140.00 /1-F $208,180.00 Alt Item 18 Furnish and install special bridge rail per Section 04 Sheet 57 76LF $140.00 /1-F $ 10,640.00 Total Deductions $218,820.00 Add the following to the contract: Concrete bridge rail, wrought iron fence, and railing on bike : path below bridge 1563LF $17.00 /LF $339,171.00 # ��l Total Additions $339,171.00 Total net change to the contract is: $ 120,351.00 Rebcon will require an additional 20 working days to be added to our contract to allow this work to be constructed. Please note the following items: 1) Because of the deck construction method using precast concrete panels the outside dowel bars on the pedestals and columns may need to have the horizontal leg shortened to allow them to fit properly. 2) Dowel bars on the east bridge inside rail will not be placed 11 /4" above the slab bottom but will be some distance above the top of the precast panels. 1 868 W. NORTHWEST HWY. DALLAS, TEXAS 75220 972/444 -8230 3) Our price assumes that the detail of the typical balluster sheet S1 A of 9 has 3- #6 on both sides of balluster top and that the vertical leg of the #5 dowel is 2.75'. 4) We are disregarding the plan view and its dimensions on sheet S1 of 9 in lieu of dimensions and layout shown on SIB of 9. 5) We have budgeted expansion joint cost in our price but need to know locations for those joints. We feel that the wingwall /column joint should also go at armor joints. We need to know where you want the rail joints. 6) We do not have any additional deck steel in our price or additional strands in the beam to carry the additional loading. If any of this will be required we will need to change our price. Please let us know as soon as possible, if the City wants us to construct this rail. It is very important iii keeping ihis job m%:viiig. If you have any questions, please let me know. Yours Very Truly, R N INC. R.E. urgett President V cc: Ulys Lane III, P.E. Wier and Associates, Inc.