DR8902-CS 890912S'YB CONSTRUCTION CO., INC.
Certified WBE - Dallas/Fort Worth P.O. Box 13614
Arlington, TX 76094-0614
Metro (817) 261-0226
Mr. Gabe Favre
'Ginn, Inc, Consulting Engineers
17103 Preston Road
Suite 100
LB 118
Dallas, Texas 75248
RE: Bethel School Road/Pelican Lane Drainage Improvements
Dear Mr. Favre:
Due to not receiving a letter ( easement ;~greemeut ) for the work on site #3,
Pelican Lane and Blue Jay until Thursday afternoon, September 7, 1989, we
would like to request an extension on this project of 10 working days.
Also, we have had approximately 5 days loss time due to rain through the
llth of September. We would like to have 5 days extension dur to this delay.
Total working days requested 15
Total calendar days 21
Contract completion date extended to October 6th, 1989.
Your consideration of this matter will be greatly appreciated. If you have any
questions please give me a call at the office.
Sincere].y,
Rick Bennett