Loading...
ST9802-CS 99120812/08/99 WED 09:03 FAX 214 361 5573 HALFF ASSOC INC Weekly Progress Report Dividend Drive Project Progress Report No. 15 Date: December 7, 1999 Time: 3:30 PM Temp: 50's Weather: cloudy Contr. McMahon Contracting, Inc. Crew: 3 Equip.: 2 paving machines, dozer, roller, water truck, 2 equipment trucks Halff Associates arrived on site at approximately 3:30 pm on December 7 for . construction observation. The water valve has been raised and the manhole is currently being raised near the monument sign at the intersection of Freeport Parkway and Dividend Dr. The cone of the manhole has been constructed, but the lid and the rim have not been installed yet. Approximately 80% of Dividend Dr. has been paved including the concrete header at the end of the street. The inlet tops, Ieave outs for the inlets, the two circle areas, and driveways have not yet been paved. At this point, all of the joints have been sawed but have not been sealed. The sanitary sewer at STA 5 +51 has been paved over and does not appear to be accessible. The storm sewer manhole at STA 9 +09 also appears to have been paved over. These two manholes will have to be accessible prior to project approval. It has been a pleasure working with you on this project. If you have any comments or questions, please contact me by phone at (214) 346 -6246 or by fax at (214) 361 -5573. Todd Jackson HALFF ASSOCIATES, INC. LFAM cc: Robert McCann, Catellus Development Corporation Bruce Roebuck, McMahon Contracting, Inc.