Loading...
ST9802-CS 99120112/01/99 WED 15:56 FAX 214 361 5573 HALFF ASSOC INC a002 Weekly Progress Report Dividend Drive Project Progress Report No. 14 Date: December 1, 1999 Time: 12:30 PM Temp: 60's Weather: sunny Contr. McMahon Contracting, Inc. Crew: 12 Equip.: 2 paving machines, dozer, roller, scraper Halff Associates arrived on site at approximately 12:30 pm on December 1 for construction observation. The concrete for the left turn lane on Freeport Parkway has been poured and the joints have been sawed. Barricades are up and functioning properly. The joints have not yet been sealed. Approximately 40% of the steel rebar has been installed and tied together on Dividend Dr. The water valve has been raised and the manhole is currently being raised near the monument sign at the intersection of Freeport Parkway and Dividend Dr. The top of the manhole has been removed and rebar is being installed in order raise the manhole. It has been a pleasure working with you on this project. If you have any comments or questions, please contact me by phone at (214) 346 -6246 or by fax at (214) 361 -5573. Todd Jackson HALFF ASSOCIATES, INC. cc: Robert McCann, Catellus Development Corporation Bruce Roebuck, McMahon Contracting, Inc.