Weekly Progress Report
Dividend Drive Project
Progress Report No. 13
Date:
October 26, 1999
Time:
10:30 AM
Temp:
70's
Weather: sunny
Contr.
McMahon Contracting, Inc.
Crew:
0
Equip.:
none
Halff Associates arrived on site at approximately 10:30 am on October 26 for
construction observation. There has been no work observed since the last Progress Report
dated October 5, 1999. The storm manhole lids at STA 2 +43 and STA 9+09 — Line A
need to be "storm sewer" lids, not "water" lids. Chris Waddle with North Texas
Contracting stated that the water line has passed all of its tests. I need a copy of these test
results from North Texas. Chris also stated that the first sanitary sewer joint downstream
of the manhole at STA 5 +51 has dropped down slightly at the manhole. I will discuss
this with Garreth Campbell to determine if any action is required to fix the situation.
It has been a pleasure working with you on this project. If you have any comments or
questions, please contact me by phone at (214) 346 -6246 or by fax at (214) 361 -5573.
Todd Jackson
HALFF ASSOCIATES, INC.