ST9802-CS 99092809/''8/99 TUE 11:50 FAX 214 361 5573 HALFF ASSOC INC Weekly Progress. Report Dividend Drive Project Progress Report No. l 1 Date: September 28, 1999 Time: 10:30 AM Temp: 80's Weather: sunny Contr. McMahon Contracting, Inc. Crew: 0 Equip.: dozer, sheep's foot roller Halff Associates arrived on site at approximately 10:30 am on September 28 for construction observation. There have been no changes made to the left turn lane area on Freeport Parkway. The irrigation system and the landscaping near the monument sign at the intersection of Freeport Parkway and Dividend Drive have not yet been repaired. Backfill is needed immediately under the monument sign for support. Garreth and I still need a copy of the original video inspection of the sanitary sewer from North Texas Contracting that has already been performed. The storm manhole top at STA 9 +09 — Line A needs to be a "storm sewer" top, not a "water" top. It appears that the utility contractor has moved out. It has been a pleasure working with you on this project. If you have any comments or questions, please contact me by phone at (214) 346 -6246 or by fax at (214) 361 -5573. Todd Jackson HALFF ASSOCIATES, INC. 2002 cc: Robert McCann, Catellus Development Corporation Bruce Roebuck, McMahon Contracting, Inc.