Loading...
ST9802-CS 99092109/21/99 TUE 16:45 FAX 214 361 5573 HALFF ASSOC INC Weekly Progress Report Dividend Drive Project Progress Report No. 9 Date: September 21, 1999 Time: 2:00 PM Temp: 60's Weather: cloudy Contr. McMahon Contracting, Inc. Crew: 12 Equip.: backhoe, dozer, sheep's foot roller Halff Associates arrived on site at approximately 8:00 am on September 21 for construction observation. The irrigation system and the landscaping near the monument sign at the intersection of Freeport Parkway and Dividend Drive have not yet been repaired. I spoke with Garreth Campbell about the sanitary sewer problem under Freeport Parkway. It was decided that the City of Coppell Engineering Department needed to be notified about the situation. I spoke with Kent Collins and made him aware of the sanitary sewer problem. However, Garreth and I still need a copy of the original video inspection from North Texas Contracting that has already been performed. The concrete has been poured for the bottom and sides of all four curb inlets, the "y" inlet, and the first storm manhole. The area for the footing on the second storm manhole was being prepared/excavated. The contractor is going to leave the top of this second manhole approximately 21" lower until the paving is done. Then the manhole will be raised to grade using grade rings. The contractor will be doing the tops of manholes and inlets tomorrow. The contractor was excavating a trench and laying PVC conduit for future irrigation and electrical lines. They were backfilling with native material and compacting it with a roller. It has been a pleasure working with you on this project. If you have any comments or questions, please contact me by phone at (214) 346 -6246 or by fax at (214) 361 -5573. Todd Jackson HALFF ASSOCIATES, INC. 10002 cc: Robert McCann, Catellus Development Corporation Bruce Roebuck, McMahon Contracting, Inc.