ST9802-CS 99091419/15/99 WED 14:24 FAX 214 361 5573 HALFF ASSOC INC Summary Offsite Drainage and Paving Improvements On -site Meeting No. 4 September 14, 1999 Halff Associates arrived on site at approximately 10:30 am on September 14 to discuss construction and inspection issues. The meeting began approximately at 10:30 am and concluded at approximately 11:45 am. During this time discussions about construction and inspection issues were held; however, not all attendees were present for all discussions. I. Participants Name Organization Phone Fax1E -mail Todd Jackson Halff Associates 214- 346 -6246 214- 361 -5573 John Capko McMahon Contracting 972- 399 -1951 972 -313 -9564 Chris Waddell North Texas Contracting 972 -670 -2342 817 -430 -9207 Garreth Campbell City of Coppell 972 -304 -3685 972 -304 -3570 I1. Issues Discussed Item Action Descriktion 4.1 info The construction on the left turn lane on Freeport Parkway should begin some time next week. John Capko stated that he checks the barricades and cones around the median on Freeport Parkway on a daily basis. 4.2 McMahon The contractor was instructed by Garreth Campbell to remove and replace any portion of the existing curb around the median/left turn lane on Freeport Parkway that is damaged prior to or during construction. 4.3 North Texas The contractor stated that the 12" water to 16" water connection is currently leaking. He is going to replace the fittings and redo the connection. Garreth Campbell said that the contractor would probably be ready to test the 16" water line by the end of the week. 4.4 North Texas The contractor has attempted to pump water from the first sanitary sewer manhole. Video inspection was attempted; however, the camera became submerged going east and west under Freeport Parkway. A more extensive investigation will need to take place in order to determine the problem with the sewer line. 4.5 North Texas Silt needs to be removed from exposed storm sewer pipe prior to completion (the first manhole location). 4.6 info The contractor was installing and excavating for the water laterals and fire hydrants. One curb inlet has been poured with concrete, and one is currently being formed. Additions and corrections to these minutes should be sent to Todd Jackson by phone at (214) 346 -6246 or by fax at (214) 361 -5573 within five (5) working days. If no corrections are noted, minutes will be assumed correct. Ia 002 HALFF ASSOCIATES, INC. Todd Jackson