ST9802-CS 99091009/13/99 MON 08:15 FAX 214 361 5573 HALFF ASSOC INC 9 002 Weekly Progress Report Dividend Drive Project Progress Report No. 7 Date: September 10, 1999 Time: 2:00 PM Temp: 90's Weather: sunny Contr. McMahon Contracting, Inc. Crew: 6 Equip.: backhoe, 2 dozers, sheep's foot roller Halff Associates arrived on site at approximately 2:00 pm on September 10 for construction observation. The irrigation system and the landscaping near the monument sign at the intersection of Freeport Parkway and Dividend Drive have not yet been repaired. The contractor is finished installing the 16" water main. The water laterals, valves, and fire hydrants were being installed. The contractor moved the two curb inlets at STA 2 +70 to the east 4 feet after talking to Garreth Campbell to better facilitate the lateral connection. A concrete truck arrived on site and began pouring concrete for one of the above mentioned curb inlets. Again, water had to be pump out of the first sanitary sewer manhole. The contractor believes there is a problem with the existing sanitary sewer line somewhere under Freeport Parkway. More information will be available when the sanitary sewer line gets video taped sometime next week. The property owner to the east stopped by the site and asked that the stockpile of native material that was on his site be removed immediately. The contractor began relocating the stockpile. It has been a pleasure working with you on this project. If you have any comments or questions, please contact me by phone at (214) 346 -6246 or by fax at (214) 361 -5573. Todd Jackson HALFF ASSOCIATES, INC. cc: Robert McCann, Catellus Development Corporation Bruce Roebuck, McMahon Contracting, Inc.