ST9802-CS 99090709/08/99 WED 09:05 FAX 214 361 5573 HALFF ASSOC INC Q 002 Weekly Progress Report Dividend Drive Project Progress Report No. 6 Date: September 7, 1999 Time: 4:00 PM Temp: 90's Weather: sunny Contr. McMahon Contracting, Inc. Crew: 6 Equip.: backhoe, 2 dozers, sheep's foot roller Halff Associates arrived on site at approximately 4;00 pm on September 7 for construction observation. The irrigation system and the landscaping near the monument sign at the intersection of Freeport Parkway and Dividend Drive have not yet been repaired. Backfill has been placed under the monument sign to better support the sign. The entire storm sewer trunk main has been installed except the manholes. The contractor is going to install 6' diameter storm manholes instead of 5' diameter manholes to better facilitate the connection of the storm pipe to the manhole. The contractor is almost finished installing the 16" water main. Only about 5 or 6 joints still needed to be installed. The water line is being backfilled with sand material then native material. Caution tape is being laid in the trench within the native backfill layer. The water laterals were also being installed, and 1 fire hydrant has been installed. The contractor is installing the water laterals under the storm sewer instead of over as the plans show. The contractor was not comfortable with the about of cover. He is going to concrete encase the water laterals that are installed under the storm sewer. It has been a pleasure working with you on this project. If you have any comments or questions, please contact me by phone at (214) 346 -6246 or by fax at (214) 361 -5573. Todd Jackson HALFF ASSOCIATES, INC. cc: Robert McCann, Catellus Development Corporation Bruce Roebuck, McMahon Contracting, Inc.