ST9802-CS 99082408/25/99 _WED 07_4 FAX 214 361 5573 HALFF ASSOC INC 9002 Weekly Progress Report Dividend Drive Project Progress Report No. 4 Date: August 24, 1999 Time: 9:00 AM Temp: 90's Weather: sunny Contr. McMahon Contracting, Inc. Crew: 10 Equip.: 3backhoes, 2 dozers, sheep's foot roller Halff Associates arrived on site at approximately 9:00 am on August 24 for construction observation. The irrigation system and the landscaping near the monument sign at the intersection of Freeport Parkway and Dividend Drive have not yet been repaired. The crew was installing the storm sewer laterals. The entire trunk main has been installed except the manholes. Crushed rock was being used for the embedment and select backfill was being used before the native material was being backfilled. The contractor stated he will install all storm sewer laterals on the south side of the main line and approximately 2 joints of the storm sewer laterals on the north side of the main line. The water line will be installed prior to finishing the north storm sewer laterals because the water line is lower. The contractor stated they should be starting the water line installation by Thursday, August 25, 1999. Erosion control methods (plywood) were being used to block exposed RCPs at the end of the work day. A dozer was excavating the existing trees in the median of Freeport Parkway which are to be removed for the installation of the left turn lane. It has been a pleasure working with you on this project. If you have any comments or questions, please contact me by phone at (214) 346 -6246 or by fax at (214) 361 -5573. Todd Jackson HALFF ASSOCIATES, INC. cc: Robert McCann, Catellus Development Corporation Bruce Roebuck, McMahon Contracting, Inc.