Loading...
ST9802-CS 99081008/11/99 WED 07:43 FAX 214 361 5573 HALFF ASSOC INC 1002 Weekly Progress Report Dividend Drive Project Progress Report No. 2 Date: August 10, 1999 Time: 3:30 PM Temp: 100's Weather: sunny Contr. McMahon Contracting, Inc. Crew: 6 Equip.: backhoe, dozer, sheep's foot roller Halff Associates arrived on site at approximately 3:30 pm on August 10 for construction observation. The sanitary sewer manhole at STA 1 +00 on the design drawings has been installed. The backfill has been installed and compacted up to about 2 ft. from the top of the manhole. The irrigation system and the landscaping near the monument sign at the intersection of Freeport Parkway and Dividend Drive have not yet been repaired. Sanitary sewer has been installed all the way to STA 5 +51. The backhoe was excavating for the installation of the 6" lateral and the manhole. The trench safety system was in place. Crushed rock was being used for the embedment. TXU was on site removing the existing light pole in the median of Freeport Parkway. The pole was successfully removed while the base is still on the ground. It has been a pleasure working with you on this project. If you have any comments or questions, please contact me by phone at (214) 346 -6246 or by fax at (214) 361 -5573. Todd Jackson HALFF ASSOCIATES, INC. cc: Robert McCann, Catellus Development Corporation Bruce Roebuck, McMahon Contracting, Inc.