Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
ST0502B-EM050131
R1W width (ft) street length (ft) paving width (ft) avg. cut (ft) sidewalk (ft) R1W needed (SF) 110 3400 66 2 5 374,000 Freeport Parkway Sandy Lake to SH 121 Excavation (CY) Stabilized sub grade (SY) Lime (tons) Concrete paving (SY) Sidewalk (SF) Mobilization & RIW prep. Drainage Incidentals Right of way Engineering Design Geotechnical Contingency Total Cost Ouanitv 27704 26444 595 24933 34000 8% 30% 35% 374000 15% NCTCOG participation per 02/05 MOU Total City Cost I Budget # - $1,200,000 Cost $10.0 $2.5 $100.0 $30.0 $4.0 $4.0 S,O S 02...1) Total $277,037 $66,111 $59,500 $748,000 $136,000 $1,286,648 $102,932 $385,994 $450,327 $2,225,901 $1,496,000 $400,000 $35,000 $4,156,901 $623.535 $4.780.436 $3,640,000 $1,140,436 rev. 1/31/05 Freeport sandy lake to sh121 cip.xls 1/31/05