DR8801-CN 881102 CITY OF COPPELL ~l~lEr ROAE pOstal Site to Freeport CHANGE ORDER No. 1 Y 'S INTENT The intent of this change order is to modify the provisions of the contract entered into by the City of Coppell and Buckelew Construction Company, dated September 28, 1988. DESCRIPTION OF CHANGES Modify the design of the box culvert on sheet 5/7 between stations 0:36.93 to 1+90. Proposed box culvert will be modified to substitute a cast-in-place design type SC-NC for the precast design C-850. Item 16, Reinforced Concrete Single Box Culvert - C850, is deleted from the contract. Add item 16A, Reinforced Concrete Single Box Culvert SC-NC, 3600 psi, to the contract amount. The Contractor agrees to pump out the existing open channel constructed to the west of this project when directed during the term of this contract. EFFECT OF CHANGES The net effect of changes described should be a decrease in the total amount of the..~ontract as follows: Item 16 - Reinforced Concrete Single Box Culvert - C850 230 x $260 = $59,800 0 Decrease $ 59,800 Item 16A Reinforced Concrete Single Box Culvert - SC-NC 230 x $220 = $50,600 Add _,$ 50,600 TOTAL, CHANGE, THIS CHANGE ORDER No. 1Deduct $ 9,2OO The revised contract amount is determined as follows: Original Contract Amount in Proposal Change Order No. 1[DEDUCT] REVISED CONTRACT AMOUNT q73,929.50 9,200.00 ~6~,729.50 City of Coppell Change Order No. 1 November 1, 1988 Page 2 AGREEMENT By the signature below, duly authorized agents of the City of Coppell and Buckelew Construction Company do hereby agree to append this Change Order No. I to the original contract between themselves dated September 28, 1988. BUCKELEW CONSTRUCTION COMPANY Contractor Signature ~ Name ~L~~~fa-T' ~:;> · '~r~C- Title ~ .(~' CITY OF COPPELL Owner Signature Name Title Date