Loading...
ST0301-CS040617 (2) ?TD}Ol bl '7/4- ~i.~ I CPL03243 Bethel Road Bridge, City of Coppell Alternative one: close the street; redirect traffic; remove existing bridge and reconstruct the bridge . It may take a minimum of 6 months to remove and reconstruct the bridge so rerouting the traffic will also need at least the same amount of time. Alternative two: provide a temporary bridge; remove existing bridge and reconstruct the bridge . Construction cost and design effort for temporary plus permanent bridges will be greater. . Need more ROW for temporary bridge? May not be feasible to obtain additional ROW. . Additional design effort can be minimized, if contractor is responsible for the design and construction of the temporary bridge is specified in the specification. Additional design effort is still needed to provide the specification and the associated work. Alternative three: maintain one lane open during construction by removing existing bridge and constructing new bridge at two stages . Alternative 3a: remove existing bridge and construct new bridge at two stages o Traffic on one-lane bridge needs to be managed. Management of traffic --- may not be feasible. o Existing bents (supported by two columns) cannot be removed until the first half of new bridge built and open in operation. o Vertical clearances (between top existing bents and bottom proposed roadway) are not adequate for new I-beams; proposed roadway would need to be raised o Additional investigations/survey will be required upfront to obtain sufficient data to allow demolition and reconstruction of existing abutments. o To maintain a viable roadway width and allow for traffic barriers, only a small portion of existing deck can be removed so new deck has to be much wider to accommodate future one lane of traffic o Shallow depth of beams will extend length of bridge and increase cost o Temporary shoring will be required to retain existing embankment after existing abutments are demolished o Shallow beams are not any cheaper since they are not used very often o Construction cost and design effort will be greater. It may take an additional 50% of design/drafting effort. . Alternative 3b: retain and reuse existing bents and abutments, add additional short piece of new bent and abutment at each side of each existing bent and abutment o Traffic on one-lane bridge needs to be managed. Management of traffic may not be feasible. o This approach can be accomplished by using same pan joists as existing for new beams (same depth and spacing) so that no changes are made in loading pattern (still uniform load). Add additional reinforced concrete on top of the existing bents and abutments to improve existing members' strength capacity. o Considerable saving on construction cost due to no demolition on bents and abutments; only new extension needed for the bents and abutments. o To maintain a viable roadway width and allow for traffic barriers, only a small portion of existing deck can be removed so new deck has to be much wider to accommodate future one lane of traffic o Further investigation is needed to ensure this approach is feasible to construct. o Current TxDOT standard drawings for pan joists and slab may not fit the existing bents and abutments. Special design and drafting for pan joists, bents and abutments may be needed o It is risky without knowing the strength capacities of the existing members (drawings for existing bridge are not available). Additional funds will be required for non-destructive testing to determine existing reinforcing in the existing members. o Additional investigations/survey will be required up front to obtain sufficient data to design the bridge. o May need to redo the design using other approach, if investigations find out that the existing members cannot support the proposed bridge loads. o Construction cost and time may be greater due to more complex construction approach is involved. Design/drafting effort will be greater. It may take additional 50% of design/drafting effort.