Lauth Park-CS061130 (2)DEVELOPMENT FEE TABLE
Project: Lauth - Coppell
Date: 11/30/2006
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
FILING
PLAT
Water Impact Fee $8,550.00
(100% due at Issuance of Building Permit)
Water Tap Inspection Fee $200.00
(100% due at Issuance of Water Meter)
Water Meter Fee (Domestic) $62.74
(100% due at Issuance of Water Meter)
Water Meter Fee (Irrigation/Fireline) $9,286.84
(100% due at Issuance of Water Meter)
Water Meter Deposit (Domestic) $30.00
(100% due at Issuance of Water Meter)
Irrigation/Fireline Meter Deposit $90.00
(100% due at Issuance of Water Meter)
Wastewater Impact Fee $1,503.00
(100% due at Issuance of Building Permit)
Wastewater Tap Inspection Fee $50.00
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee $50.00
(100% due at Issuance of Building Permit)
Park Fee $0.00 $0.00
(100% due prior to Filing Plat)
Roadway Impact Fee $183,109.65 $183,109.65
(100% due prior to Filing Plat)
Street Light Fee Information not Avai lable
(100% due prior to Acceptance of Project)
Street Sign Fee Information not Available
(100% due prior to Acceptance of Project)
Construction Inspection Fee Information not Available
(100% due prior to Start of Construction)
TOTAL $202,932.23
TOTAL AMOUNT DUE PRIOR TO FILING FINAL P LAT $183,109.65
DEVELOPMENT FEE WORKSHEET
PROJECT: Lauth - Coppell
DATE: 11/30/2006
Water Impact Fee:
Domestic Meter(s)
Irrigation Meter(s):
Fireline Meter(s):
1 - 1 inch
1 - 2 inch
0
2 - 8 inch
Total #: 9.5 ESU's @ $900.00 ea.
(Due prior to issuance of building permit}
= 1.67 ESU's
= 5.33 ESU's
= 0 ESU's
= 2.5 ESU's
Water Tap Inspection Fee:
Total #: 4 Connections @ $50.00 ea.
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Domestic Water Meter Fee:
Total #: 1 Domestic Meter(s) @ $62.74
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Irrigation/Fireline Water Meter Fee:
$8,550.00
$200.00
$62.74
Total #: 1 Irrigation Meter(s) @ $204.34 $204.34
Total #: 0 Additional Irrigation Meter(s) @ $0.00 $0.00
Total #: 2 Fireline Meter(s) @ $4,541.25 $9,082.50
(100% due prior to issuance of water meters)
Domestic Water Meter Deposit Fee:
Total #: 1 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Irrigation/Fire Meter Deposit Fee:
Total #: 3 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Wastewater Impact Fee:
Total Domestic Meters ESU's: 1.67
(Due prior to issuance of building permit)
@ $900.00 ea
Wastewater Tap Inspection Fee:
Total #: 1 Connections @ $50.00 ea.
(100% due prior to issuance of building permit)
Utility Final Inspection Fee (All developments):
Total #: 1 Lots @ $50.00 ea.
(100% due prior to issuance of building permit)
$30.00
$90.00
$1,503.00
$50.00
$50.00
Page 1
DEVELOPMENT FEE WORKSHEET
Park Fee (For Residential Developments Only):
* Preliminary plat approved:
0 Single-family @ $0.00 per lot
0 Multi-family @ $0.00 per unit
(100% paid prior to Council approval of final plat)
Roadway Impact Fee:
(See attached fee calculations)
Street Lighting Fees:
Assessed for lighting in the City's right-of-way.
This fee cannot be assessed until after T.U. Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.60 per light will be assessed.
(100% due prior to final acceptance of development)
Street Sign Fees:
Assessed for signage in the City's right-of-way.
(See attached fee calculations if applicable)
Construction Inspection Fees:
A copy of the development contract must be submitted for assessment.
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
$0.00
$0.00
$183,109.65
Information not Available
Information not Available
Information not Available
Page 2
ROADWAY IMPACT FEE CALCULATIONS
PROJECT: Lauth - Coppell
DATE: II/30/2006
ROADWAY IMPACT FEE:
Service Area * 1
Cate ory ** Office
Land Use ** MedicaUDental Office
Buildin Area (sf) 68,350
Develo ment Units ** 68.35
Vehicle Miles er Develo ment Unit ** 17.86
Fee er Vehicle Mile *** $150
Roadway Impact Fee due = (Development Units) x
(Vehicle Miles er Develo ment Unit) x (Fee er Vehicle Mile) _
$183,109.65
* (Figure 4.1 -Roadway Impact Fee Study)
** (Table 4.10 -Roadway Impact Fee Study)
*** (Schedule 2, Page 3 -The Master Fee Schedule)
check credit from old beal property