CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: West Sandy Lake Road Project # ST 99-02A
CONTRACTOR: Tiseo Paving Company
OWNER: City of Coppell
..
CHANGE ORDER NO.:
Five (5)
DATE: February 15, 2007
Item Description
ADD: Remove existing grate and
install 'Y' inlet top w/two
open sides
Total Revision to Contract Amount Change Ord. #5
Quantity Unit Unit Price
1 LS 2,090.00
Total
$2090.00
Original contract amount
Net increase in contract amount Change Order # 1 5/9/06
Net increase in contract amount Change Order # 25/17106
Net increase in contract amount Change Order # 3 11/2/06
Net increase in contract amount Change Order # 41/8/07
Net increase in contract amount Change Order # 5 2/15/07
Revised contract amount
$2,090.00
$3,961,787.00
15,635.00
2,900.00
6,737.00
2,250.00
2,090.00
$3,991,399.00
10 Day
310 Calendar Days
Net increase in contract time of completion
Revised Contract time of completion
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract by
reason of this revision to the Contract.