Vistas of C P2-LR 980316oRa
FUGRO- McCLELLAND (SOUTHWEST), INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484 -8301; Fax (972) 620 -7328
OBSERVATION OF CONCRETE PLACEMENT
CLIENT: Centex Homes REPORT DATE: March 16, 1998
PROJECT: Vistas of Coppell, Phase 1B & 2C Coppell, Texas PROJECT NO: 0771 -2221
DATE PERFORMED: March 5, 9998
General Contractor: Glen Thurman Inc.
Method of Test: Applicable ACI Recommendations and ASTM Standards
Results 1 Remarks:
Concrete placement observation was performed at the Alleys and street coves, intersection Area 1A -26
following location:
Time placement began:
Time placement ended:
Total cubic yards placed:
Slump range (inches):
Slump required (inches):
Concrete supplier and plant:
Concrete temperature range ( °F):
Strength required (psi /days):
Number of cylinders made:
Superplasticizer used:
7:30 A.M.
3:30 P.M.
291
53/4
5
On site
66 -72 °F
3000/28
No
Mike Flute
Fugro - McClelland Technician
FUGRO- McCLELLAND (SOUTHWEST), INC.
Checked
SMH /mv
Distribution: Centex Homes - Robert Poole
Glenn Thurman Inc.
City of Coppell - Garreth Campbell
�[aRD
FUGRO SOUTH, INC.
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484 -8301; Fax (972) 620 -7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
CLIENT: Centex Homes Report Date March 16 1998
PROJECT Vistas of Coppell, Phase 1B &2C Coppell, Texas Project No .: 0771 -2221
SAMPLE DATE: March 3, 1998
CONTRACTOR:
TICKET NO.:
AMBIENT TEMP. (°F):
CONCRETE TEMP. (°F):
TIME BATCHED:
TIME SAMPLED:
WEATHER CONDITION:
LOCATION OF PLACEMENT:
Glenn Thurman, Inc.
CONCRETE SUPPLIER: On Site
45 PLANT/TRUCK:
58 MIX ID NUMBER:
8:45 am AIR ( % ) (ASTM C -231)
9:10 am WATER ADDED (gal): 0
Cool slightly mild SLUMP (inches) (ASTM C -143) 1.5
Paving: Lyndsie Dr. station 7 +00
CONCRETE CYLINDER C0MPRE551Vt s I Kr-NU 111-1 1 CO 10
Standard 6" x 12", 28.27 square inches
CYLINDER
NUMBER
AGE
(days)
DATE
TESTED
TOTAL LOAD
(pounds)
COMPRESSIVE
STRENGTH
(psi)
REQUIRED COMPRESSIVE
STRENGTH
(psi)
VCC 73
7
03/10/98
115000
4068
3600/28 days
VCC 74
28
03/31/98
VCC 75
28
03/31/98
VCC 76
Hold
Specifications: Making & ASTM C -31 Testing Methods: ASTM C -143, ASTM C -39
Curing:
REMARKS: Unit Weight: 146 Ibs /cu. ft.
Technician: William Freeze
FUGRO- McCLELLAND (SOUTHWEST), INC.
Checked By: -=
SMH /rm
Distribution: Centex Homes - Robert Poole
Glenn Thurman Inc.
City of Coppell - Garreth Campbell
FUGRO SOUTH, INC.
r � �
2880 Virgo Lane; Dallas, Texas 75229
Ph (972) 484 -8301; Fax (972) 620 -7328
COMPRESSIVE STRENGTH OF CONCRETE REPORT
CLIENT: Centex Homes Report Date: March 16, 1998
PROJECT Vistas of Coppell, Phase 1B &2C Coppell, Texas Project No .: 0771 -2221
SAMPLE DATE: 'March '3, 1998'
CONTRACTOR:
TICKET NO.:
AMBIENT TEMP. ( °F):
CONCRETE TEMP. (°F):
TIME BATCHED:
TIME SAMPLED:
WEATHER CONDITION:
LOCATION OF PLACEMENT:
Glenn Thurman, Inc.
CONCRETE SUPPLIER: On Site
42 PLANT/TRUCK:
51 MIX ID NUMBER:
7:30 am AIR ( %) (ASTM C -231)
7:55 am WATER ADDED (gal): 0
Cold SLUMP (inches) (ASTM c -143) 3
Paving: Lyndsie Drive, station 5 +50
CONCRETE CYLINDER COMPRESSIVE STRENGTH TESTS
Standard W' x 12 ", 28.27 square inches
CYLINDER
NUMBER
AGE
(days)
DATE
TESTED
TOTAL LOAD
(pounds)
COMPRESSIVE
STRENGTH
(psi)
REQUIRED COMPRESSIVE
STRENGTH
(psi)
VCC 69
7
03/10/98
78000
2760
3600/28 days
VCC 70
28
03/31/98
VCC 71
28
03/31/98
VCC 72
1 Hold
Specifications: Making & ASTM C -31 Testing Methods: ASTM C -143, ASTM C -39
Curing:
REMARKS: Unit Weight: 142 Ibs /cu. ft.
Technician: William Freeze
FUGRO- McCLELLAND (SOUTHWEST), INC.
Checked By:
SMH /br
Distribution: Centex Homes - Robert Poole
choose contractor
City of Coppell - Garreth Campbell