Stonemeade-CS 940221COPPELL PUBLIC WORKS
MEMORANDUM
DATE: February 21, 1994
TO: Garreth Campbell, Construction Inspector
FROM: Howard Pafford, Utilities Superin
RE: Final Walk- Through for Stonemeade Estates 24" Sanitary Sewer
Relocation
Utilities personnel performed a walk -thru on the above referenced project and the following
items were found to be deficient:
* 246 + 79.88 - Regrout outside of Manhole. Broke away when pulled lid.
* Also need access to line - either entry built on each end or somewhere in the
middle.
Please ensure that each of these items are corrected prior to release of this project.
HLP /dm