DR8801-CS 890926COPP~. PI~t~ICWORKS
TO:
FROM:
RE:
September 26, 1989
Larry
Davis, Construction Inspector
Howard Pafford, Water Utilities Superintendent
Final Walk Thru Punch List for Completion of the
Bethel Road Drainage Improvements Project
I have assigned field personnel to perform a walk thru on the above
reference project. Below you will find a list of the items found
to be deficient.
Location
Description
1. West of Minyards
Fireline Vault
10" Gate Valve Could Not Be Located
2. 10" Valve At Point
of Connection to
16" Water Line on
Bethel Road
Valve Stack Cap Needs to be Painted
and Mark On Pavement
Please make sure that these items are addressed prior to acceptance
of this project.
If you have any questions regarding this matter, please advise.
HLP/bb
xc: Steve Gor~m, Director of Public Works
Ted Dutt, Water Utilities Crewleader
BETHELRD.HLP