DR8801-CS 890808DeShazo, Starek & Tang, Inc. '~-
Engineers · Planners
/,,
:~. "...' .5- , .'/ , ,-',
TO:
FROM:
DATE:
SUBJECT:
Russell Doyle, P.E.
City Engineer
City of Coppell
David E. Lucado, P.E.
August 8, 1989
Bethel Road Drainage Improvements
Postal Site to Freeport Parkway
Construction Status
88157.04
As requested, the following status report has been prepared for
the referenced project,
Construction Progress to Date
According to our observations, construction has progressed
as follows:
Culvert Component
Bottom Slab
Walls
Top Slab
Upstream Station
20+05 (Complete)
20+05 (Complete)
20+05 (Complete)
The headwall, apron and tie-in to the existing channel lining
are complete,
2. Work in Progress
The backfilling of the culvert continues. According to the
contractor's representative, the backfill and final grading will
be completed by the end of August.
After you have an opportunity to review this report, please notify
me of any exceptions or corrections.
cc: Larry Davis