April 5, 2000
Mr. Robert C. Bibby
REBCON, Inc.
1868 W. Northwest Hwy.
Dallas, Texas 75220
Dear Robert:
I am in receipt of your faxed agreement to the terms outlined in Mr. Alen Hinckley's letter to
you, dated April 4, 2000.
I have no problem with delaying construction of Town Center Boulevard West, (Second High
School Access, ST97 -04), to facilitate off -site utility construction associated with the
development of Town Center West. I appreciate your willingness to cooperate with both the
developer and the City of Coppell.
Please understand our desire to have our project finished and ready for use by early August.
will be involved in the above mentioned construction and will inform you of any unexpected
delays or problems that may develop.
Thanks again for your cooperation.
Sincerely,
Ga et Campbell
Construction Inspector
cc: Mike Martin, P.E.
Alen Hinckley
APR -04 -00 TUE 03:59 PM REBCON, INC FAX NO. 9724448234 P.02/02
Sent By: INVESTMENTS; 972 991 7500; Apr-4-00 10:51AM; Page 2/2
ESTATE OF JOE C. HINCKLEY, E]" AL
12201 MERM Draw, SurrE t TO
DAu An, T r - xAB 7525 i
972-991-46000
April 4, 2000
Robert Bibby
Rebcon Construction
1868 West Northwest Highway
Dallas, Texas 75220
VIA FAX072hiiW8234
RE: Utility installation Town Center West City of Coppell, Texas
Dear Robert,
It has been brought to my attention that in order to timely install the utilities and lun ing
irrigation lines required on the Datail Site Plau approved by City Council March 28�', a
coordination of timing for the Town Center West paving section Is necessary. As you know, the
underground utilities need to be installed prior to the paving of Town Center West Road and
sidewalk sections.
We request you delay the lime stabilization and paving of Town Center west to allow our
contractors to complete the utility work necessary and to meet other conditions set by the City
Council.
This will confirm that Rebcon will impose no fees or penalties associated with postponing this
project.
We appmciate the efforts and coordination by the City of Coppell Engineering and Building
Inspection Staff as well as Rebcon's assistance.
Yours truly,
Estatc of a C. Hinckley et al
By: *awl kley
CC: Ken Griffin City of Coppell VIA FAX (972)304 -3570
Bill Anderson Dowdy Anderson & Assoc. VIA FAX (972)931 -9538
Jim Mills — Children's Courtyard VIA FAX (817) 468 -9521