Vista Point 2R-LR070301
REED EnGinEERinG
GEOTECHNICAL AND G R 0 U F'
ENVIRONMENTAL CONSULTANTS
REPORT OF REINFORCING
STEEL PLACEMENT OBSERVATION
Vista Point II, Phase II
S.H. 121 at MacArthur Boulevard
Coppell, Texas
REPORTED TO: Bullard Construction, Inc.
P.O. Box 575
Addison, Texas 75001
ATTN: Mr. Keith McMahon
REPORT NO. 103
REPORT DATE: 03-01-07
REG PROJECT NO. 13581
DATE OBSERVED: 02-17-07
TECHNICIAN: C. Johnson
PAGE: 1 of 1
CONTRACTOR: Bullard Construction, Inc.
I Items Observed:
I Paving: 60'N, 200'E from N.W. corner of Building 4.
I Reference Plans or Notes Used: I Sheet C8.1
x IThere were no deviations noted.
The reinforcing steel placed at the above referenced locations was observed with
respect to the referenced portions of the contract documents.
Extranet
Distribution: (1) Jackson Shaw Company/
Mr. Christopher Gardner
(1) AECC, Inc./Mr. Todd Waters
(1) Jackson Shaw Company
Ms. Michelle Graham
Submitted by:
REED ENGINEERING GROUP, LTD.
Original Signed By
Mail
Distribution: (1) Bullard Construction, Inc./
Mr. Keith McMahon
(1) City of Coppell/Mr. Keith Marvin
Ronald F. Reed, P.E.
BW/rs
2424 STUTZ DR. . SUITE 400 . DALLAS, TX 75235 . TEL [214] 3505600 . FAX [214] 3500019