DR8801-CS 890711DeShazo, Starek & Ta, ~nc.
Engineers * Planners
Un]on Station · Dallas, Texas 75202 · 214/748-6740
TO:
FROM:
DATE:
SUBJECT:
MEMORANDUM
Russell Doyle
City Engineer
City of Coppell, Texas
David E. Lucado
July 11, 1989
Bethel Road Drainage Improvements
Postal Site to Freeport Parkway
Construction Status
88157.04
As you requested, the following status report for the referenced
project has been prepared.
Field Survey
On July 5, 1989, our surveyors made a cursory field survey
of the Project to compare the actual construction with the
requirements of the plans. A copy of the results of the
survey is attached.
Horizontal accuracy varies from 0.43 ft. at P.I. Station
16+15.8 to 0.02 feet at Station 20+05.
Vertical accuracy varies from 0.16 feet above grade at Station
15+36.7 to 0.27 feet above grade at Station 20+05.
The horizontal tolerances appear to be within acceptable limits
and well within the available easement. The vertical
tolerances also appear to be acceptable. The flow lines in
the upstream section were constructed slightly higher than
proposed in order to tie in to the existing concrete apron.
2. Construction Progress
According to our measurements, construction has progressed
as follows (construction is proceeding upstream) on July 5.
Culvert Component
Upstream Station
Bottom Slab 20 + 05
Walls 20 + 05
Top Slab 16 + 95
Mr. Russell Doyle
July 11, 1989
Page 2
After you have an opportunity to review this report, please notify
me of any exceptions or corrections.
cc: Larry Davis