Villages of CC 4-CS 930525COPPELL PUBLIC WORKS
MEMORANDUM
DATE: May 25, 1993
TO: Garreth Campbell, Construction Inspector
FROM: Howard L. Pafford, Utilities Superintendent
RE: Walk - Through Punch - List for Cotton Wood Creek Estates Phase IV
(Water /Sanitary Sewer)
problems have been corrected with the exception of the following:
1�
1. Sta. 10 + 20.28 - No rise from cone top.
* 2. Sta. 0 + 00 Line B - No rise from cone top.
q 3. Sta. 0 + 00 Line C - Repair inflow into manhole invert.
3 p 4. Matheson Drive - Mainline valve under concrete.
Additionally, there are two (2) manhole connections on this project that are improperly
installed. All connections to existing manholes must be core drilled and sealed with cor -n
seal and blocked with concrete. The two connections that were made on this project fail to
meet these standards; therefore, it is necessary to excavate and pour in 3 feet x 2 feet
concrete encasement on outside of connection. It will be necessary to stabilize this blockout
and have construction inspector inspect the repair.
Please ensure that each of these items are corrected prior to acceptance of this project.
If you have any questions, please advise.
HLP /dm
cc: Steven G. Goram, Director of Public Works
COTNWOD2HLP