Paula Crocker - traffic light Whispering Hills /Sandy Lake :; Q p e 5 —
From: Ken Griffin
To: Clay Phillips; Jim Witt; Kathy Bowling
Date: 3/26/2007 1:20 PM
Subject: traffic light Whispering Hills /Sandy Lake
CC: Paula Crocker
Jim
The contractor placed his construction signs today and he should actually start work tomorrow. His
anticipated completion date is April 27th. The completion time is dependent on two things - weather
and TXU providing power. We experienced about a 2 -3 week delay on West Sandy Lake waiting on
TXU to provide power.
ken g