TR0502-CS070326Page 1 of 1 Paula Crocker - traffic light Whispering Hills /Sandy Lake :; Q p e 5 — From: Ken Griffin To: Clay Phillips; Jim Witt; Kathy Bowling Date: 3/26/2007 1:20 PM Subject: traffic light Whispering Hills /Sandy Lake CC: Paula Crocker Jim The contractor placed his construction signs today and he should actually start work tomorrow. His anticipated completion date is April 27th. The completion time is dependent on two things - weather and TXU providing power. We experienced about a 2 -3 week delay on West Sandy Lake waiting on TXU to provide power. ken g file: / /C:\ Documents% 20 and% 20 Settings \PCROCKER\Local %20Settings \Temp \GW 10000... 3/26/2007