Loading...
DR8801-CS 890320 (2) March 20, 1989 ~ ' eve Goram Direct of/~Public Works TO: St 7e Gor~o~~_ FuD±ic_worKs_____ · ,~_~ .... FROM: St ~ M_~D~~~f Public Works Inspector ~/~ RE: ~Bethel'~d./~Drainag~rovements Steve, Freeport was closed to traffic on 11/22/89 with a scheduled · reopening date of 2/1/89. Due to rain, snow, ice, and more rain we have had to reschedule the opening several times. The month of February had only six (6) non-consecutive working days due to freezing and wet conditions. I am pleased at this time to inform you that at 10:30 a.m. on today's date, we have achieved the goal of reopening Freeport to traffic. The project is at this time 48% complete and has used 46% of its time. This project is on track and should be completed on or a little ahead of schedule (7/1/89). The only difficulty was weather conditions in regards to street subgrade preparation. SMM/bb