TR0301-CN070409 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT Traffic Signal Installation Project # TR 03-01 (A) Belt Line Road @ MacArthur Blvd. & (B) MacArthur Blvd. @ Bethel School Rd. CONTRACTOR. Roadway Solutions, Inc. OWNER. City of Coppell '. .,. CHANGE ORDER NO Two (2) DATE April 3, 2007 Item Description Quantity Unit Unit Price Total DELETE 39-B Furnish and Install Standard Street Signs 1 LS 6,000 00 (6,000 00) ADD: 38-B Furnish and Install Illummated Street Signs 4 EA 2,700 00 10,800 00 Total Revision to Contract Amount $4,800.00 $298,042.00 8,006.80 4,800.00 $310,848.80 o Day PrevIous contract amount Net 1I1crease 111 contract amount Change Order #1 Net 1I1crease 111 contract amount Change Order #2 Revised contract amount Net 111crease m contract tIme of completIon ReVised Contract tIme of completIon 275 Calendar Days The contractor hereby accepts this Contract adjustment as a final and complete adjustment m full accord and satIsfactIon of all past and future lIabilIty ongmatmg under any clause 111 the Contract by reason OfthIS revIsion to the Contract. 4.3'J Date CfP/7 Date ~~l r . //\ _. _ Agreed o9y-Contractor \/ L~ 1; /, 7 Date Page 1 of 1