WA0001-CS000208 (2) Page I of 1
MONTHLY PAY REQUEST
Owner: CITY OF COPPELL, TEXAS Pay Request No.
Project: Repainting of the 1.5 Million Gallon Elevated Storage Tank Interior Contract Date: FebmaW 8, 2000
Original Contract Amount: $ 125,700.32
From: 3-Mar-00 To: 3 l-Mar-00 Revised Contract Amount:
Project Start Date: 3-Mar-2000
Contractor: Advantage Contract Services, Inc. Est. Completion Date: 2-May-2000
7150 Almeda Genoa
Houston, Texas 77075 Allotted: Used: 29
Quantity
Quantity Complete Total
Item in Revised This Work Contract Extended
No. Description Unit Proposal Quantity Request Completed Price Amount
BASE BID
1 Abrasive Blasting the Interior Area of Tank L.S. 1 $45,000.00 $
2 Paint the Interior Area of the Tank L.S. I $45,000.00 $
3 Disposal of Interior Paint & Blasting Media Removed L.S. 1 $5,000.00 $
4 Miscellaneous Remedial Welding by a Certified Welder Hrs. 10 $85.00 $
5 24" Motor Operated Butterfly Valve L.S. I $7,500.00 $
6 Electric Dehumidification System for Interior Blast, Paint &Cure L.S. 1 $18,850.00 $
ADD1TIVE ALTERNATE
1A Safety Climb Device on Existing Dry &Wet Ladders L.F. 131 $26.72 $
Prepared and Submitted by:
SHIMEK, JACOBS & FINKLEA, L.L.P.
Consulting Engineers, Dallas, Texas Total Amount $
By: Less Amount Retained 10% $
Gary C. Hendricks, P.E.
Date: Total Amount Payable $
Approved for Owner Less Previous Payments $
By:
Date: Amount Due This Request $ - ]
J:\Coppell'/99176/~ay-rqst\Pay-reql .xls